PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-07-07⁩
ApprovedCRT-010-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Rami Youssef
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦3%⁩
DueAuto-filled
⁦2025-06-10⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-010_1.1_v1.pdfV1Eng. Rami Youssef⁦2025-03-02⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Wassim Al-Azm
Accepted byAuto-filled
Salma Al-Zaim
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2025-005
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2025-03-02⁩ 11:50
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-03-03⁩ 09:54
3Inspection & technical acceptance — ownerTechnical acceptanceSalma Al-ZaimProject ownerOn behalf of Eng. Wassim Al-AzmApprovedInspected and accepted against the approved acceptance criteria.⁦2025-03-05⁩ 10:01
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-03-09⁩ 12:45
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-03-10⁩ 13:22

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2025-03-03⁩

Inspection & technical acceptance — owner

Salma Al-Zaim

Approved⁦2025-03-05⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2025-03-09⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2025-03-10⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Rami Youssef on ⁦2025-03-02⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-03-03⁩ at ⁦09:54⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-03-05⁩ at ⁦10:01⁩ · On behalf of Eng. Wassim Al-Azm (Salma Al-Zaim)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-03-09⁩ at ⁦12:45⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-03-10⁩ at ⁦13:22⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-03-02⁩

    PRJ-2026-010_1.1_v1.pdf

    Eng. Rami Youssef

Only one version so far.