PRJ-2026-032On track5ClosureAgileCompletedDelivered by:Ministry of Administrative Development

Government HR System — Employee Self-Service

Add to watchlist

Self-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.

Budget (BAC)

SYP 285M

Actual cost

SYP 268.9M

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 268.9M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+7

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦100% done against 100% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦06⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Human DevelopmentSO-3.2Develop human capital in public bodies

Main initiative

SI-1.1.1Integrated government financial systems

Contribution to the initiative⁦13%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2024-032
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦100%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦0%⁩

11 deliverables accepted

  • Release 1⁦13%⁩
  • Release 2⁦13%⁩
  • Integrations⁦13%⁩
  • System testing⁦10%⁩
  • User acceptance testing⁦10%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦9%⁩
  • Training & change⁦8%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦5⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦96%⁩ of budget

    SYP268.9M/ SYP285MSYP16.1Mprojected saving(⁦5.7%⁩)
    Actual spend
    SYP268.9M
    Committed
    SYP272.5M
    Approved budget
    SYP285M
    Estimate at completion
    SYP268.9M

    Next milestones

    • Every milestone is complete

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SYP 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦11⁩ of ⁦11⁩ approved

    • Project plan & baseline032-D1 · V1 · CRT-032-01⁦4%⁩Nour Al-Jabiri2024-07-152024-07-15Approved
    • Monitoring & reporting032-D2 · V1 · CRT-032-02⁦4%⁩Muhannad Al-Homsi2024-08-282024-08-28Approved
    • Business requirements032-D3 · V1 · CRT-032-03⁦9%⁩Muhannad Al-Homsi2024-10-112024-10-11Approved
    • Solution design032-D4 · V1 · CRT-032-04⁦9%⁩Salma Al-Zaim2024-11-242024-11-24Approved
    • Release 1032-D5 · V1 · CRT-032-05⁦13%⁩Salma Al-Zaim2025-01-082025-01-08Approved
    • Release 2032-D6 · V1 · CRT-032-06⁦13%⁩Nour Al-Jabiri2025-02-212025-02-21Approved
    • Integrations032-D7 · V1 · CRT-032-07⁦13%⁩Muhannad Al-Homsi2025-04-062025-04-06Approved
    • System testing032-D8 · V1 · CRT-032-08⁦10%⁩Nour Al-Jabiri2025-05-202025-05-20Approved
    • User acceptance testing032-D9 · V1 · CRT-032-09⁦10%⁩Muhannad Al-Homsi2025-07-042025-07-04Approved
    • Training & change032-D10 · V1 · CRT-032-10⁦8%⁩Muhannad Al-Homsi2025-08-172025-08-17Approved
    • Go-live & handover032-D11 · V1 · CRT-032-11⁦7%⁩Salma Al-Zaim2025-09-302025-09-30Approved

    Team, contracts & documents

    Team

    1 member

    Nour Al-Jabiri · Director, Government Systems & Integration
    • Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationProject managerP-025nour.aljabiri@psa.gov.sy⁦0%⁩