1.00Schedule performance index · 1.001.06Cost performance index · 1.06
Forecast finish
2025-09-21
On baseline
Closure·Stage 5 of 5
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Baselines
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Original baseline
v1.0Approved & lockedVersion A
Finish
2025-09-30
Budget
SYP 285M
16 activities
Approved with the project plan at the planning gate.
Approved 2024-05-05 · by Salma Al-Zaim
Working
Working baseline
v2.0-draftWorking draftVersion B
Finish
2025-09-21
−9 days
Budget
SYP 285M
16 activities
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Each line starts at the milestone’s date in A and ends at its date in B
2025-012025-07
Project plan approved−2
Designs approved−3
Build complete−6
Testing & acceptance complete−8
Final handover−9
Version AVersion B
Cost by WBS element
Difference in SYP millions from A to B
1Management & governance−0.95
2Analysis & design−2.02
3Build+0.96
4Testing & acceptance−2.37
5Launch & handover−1.78
Version history
Every saved version with its reason and reference
Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.2026-10-28by Nour Al-Jabiri
Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.2024-05-05by Salma Al-Zaim