PRJ-2026-032On track5ClosureAgileCompletedDelivered by:Ministry of Administrative Development

Government HR System — Employee Self-Service

Add to watchlist

Self-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.

Budget (BAC)

SYP 285M

Actual cost

SYP 268.9M

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 268.9M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 285M split into spent, committed and left, with the estimate at completion

EAC SYP 268.9M
Revised request SYP 285M
  • Actual spendSYP 268.9M
  • Committed, not spentSYP 3.6M
  • Allotted, uncommittedSYP 4M
  • Contingency availableSYP 8.6M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 277.5M
Original budgetwhen the first baseline was approved
SYP 285M
Approved budgetafter approved change requests
SYP 285M
Current budgetavailable to spend now
SYP 285M
Revised budgetif the pending changes are approved
SYP 285M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 272.5M
Contracts1 active contract
SYP 220M
Purchase orders⁦2⁩ orders
SYP 52.5M
Remaining budgetapproved less actual
SYP 16.1M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 268.9M
Accrualswork done, not yet invoiced
SYP 10.8M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 268.9M
ContingencySYP 5.7M drawn of SYP 14.3M
SYP 8.6M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 277.5M
ApprovedSYP 285M
Estimate at completionSYP 268.9M
Approved is SYP 7.5M (⁦2.7%⁩) above the estimate
The estimate at completion is SYP 8.6M (⁦3.1%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-02-20⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61032
  • WBS elements⁦5⁩ elements · P-2026-032.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦11⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 5.7M drawn of SYP 14.3M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 5.7M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance22.1221.8021.5121.17⁦+0.95⁩
2Analysis & design47.0046.3245.7144.98⁦+2.02⁩
3Build110.58109.00107.55105.84⁦+4.74⁩
4Testing & acceptance55.2954.5053.7752.92⁦+2.37⁩
5Launch & handover41.4740.8840.3339.69⁦+1.78⁩
Unallocated contingency8.550.000.004.28⁦+4.28⁩
Total285.00272.50268.87268.87⁦+16.13⁩

Budget split

WBS

SYP 285M

Budget

  • Management & governanceSYP 22.1M⁦8%⁩
  • Analysis & designSYP 47M⁦16%⁩
  • BuildSYP 110.6M⁦39%⁩
  • Testing & acceptanceSYP 55.3M⁦19%⁩
  • Launch & handoverSYP 41.5M⁦15%⁩
  • Unallocated contingencySYP 8.6M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2025-09-30⁩

SPI(t) ⁦1.00⁩ against the approved finish ⁦2025-09-30⁩

Planned valuePV
SYP 285M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 285M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 268.9M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 285M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+16.13⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.06
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 268.9M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+16.13⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 268.9M
  • If the rest goes to planSYP 268.9M
  • At cost and schedule performanceSYP 268.9M
  • The PM’s bottom-up estimateSYP 268.9M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 268.9M

Variance at completion: ⁦+16.13⁩ SYP M