Government HR System — Employee Self-Service
Add to watchlistSelf-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.
Budget (BAC)
Actual cost
94% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-08-28 | 2024-08-26 | −2 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2024-11-24 | 2024-11-21 | −3 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-04-06 | 2025-03-31 | −6 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2025-07-04 | 2025-06-26 | −8 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2025-09-30 | 2025-09-21 | −9 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline032-D1 | 4% | CRT-032-01 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Muhannad Al-Homsi | 2024-07-15 | V1 | 3 of 3 |
| Monitoring & reporting032-D2 | 4% | CRT-032-02 | Approved | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | Muhannad Al-Homsi | 2024-08-28 | V1 | 3 of 3 |
| Business requirements032-D3 | 9% | CRT-032-03 | Approved | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | Muhannad Al-Homsi | 2024-10-11 | V1 | 3 of 3 |
| Solution design032-D4 | 9% | CRT-032-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Muhannad Al-Homsi | 2024-11-24 | V1 | 3 of 3 |
| Release 1032-D5 | 13% | CRT-032-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Muhannad Al-Homsi | 2025-01-08 | V1 | 3 of 3 |
| Release 2032-D6 | 13% | CRT-032-06 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Muhannad Al-Homsi | 2025-02-21 | V1 | 3 of 3 |
| Integrations032-D7 | 13% | CRT-032-07 | Approved | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | Muhannad Al-Homsi | 2025-04-06 | V1 | 3 of 3 |
| System testing032-D8 | 10% | CRT-032-08 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Muhannad Al-Homsi | 2025-05-20 | V1 | 3 of 3 |
| User acceptance testing032-D9 | 10% | CRT-032-09 | Approved | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | Muhannad Al-Homsi | 2025-07-04 | V1 | 3 of 3 |
| Training & change032-D10 | 8% | CRT-032-10 | Approved | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | Muhannad Al-Homsi | 2025-08-17 | V1 | 3 of 3 |
| Go-live & handover032-D11 | 7% | CRT-032-11 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Muhannad Al-Homsi | 2025-09-30 | V1 | 3 of 3 |
| Total · 11 | 100% |