PRJ-2026-032On track5ClosureAgileCompletedDelivered by:Ministry of Administrative Development

Government HR System — Employee Self-Service

Add to watchlist

Self-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.

Budget (BAC)

SYP 285M

Actual cost

SYP 268.9M

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 268.9M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-05-30⁩
ApprovedPRJ-2026-032Government HR System — Employee Self-Service

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-032
Project
Government HR System — Employee Self-Service
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Salma Al-Zaim
Project manager
Nour Al-Jabiri

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-05-05⁩

Baseline finish

⁦2025-09-30⁩

Forecast finish

⁦2025-09-21⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2024-08-28⁩⁦2024-08-26⁩−2 days
Designs approved⁦2024-11-24⁩⁦2024-11-21⁩−3 days
Build complete⁦2025-04-06⁩⁦2025-03-31⁩−6 days
Testing & acceptance complete⁦2025-07-04⁩⁦2025-06-26⁩−8 days
Final handover⁦2025-09-30⁩⁦2025-09-21⁩−9 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2024-07-15⁩Nour Al-Jabiri
Monitoring & reporting⁦4%⁩⁦2024-08-28⁩Muhannad Al-Homsi
Business requirements⁦9%⁩⁦2024-10-11⁩Muhannad Al-Homsi
Solution design⁦9%⁩⁦2024-11-24⁩Salma Al-Zaim
Release 1⁦13%⁩⁦2025-01-08⁩Salma Al-Zaim
Release 2⁦13%⁩⁦2025-02-21⁩Nour Al-Jabiri
Integrations⁦13%⁩⁦2025-04-06⁩Muhannad Al-Homsi
System testing⁦10%⁩⁦2025-05-20⁩Nour Al-Jabiri
User acceptance testing⁦10%⁩⁦2025-07-04⁩Muhannad Al-Homsi
Training & change⁦8%⁩⁦2025-08-17⁩Muhannad Al-Homsi
Go-live & handover⁦7%⁩⁦2025-09-30⁩Salma Al-Zaim
Accepted with a certificate⁦100%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyNour Al-Jabiri
Project ownerDeliverable status and acceptance datesFortnightlyNour Al-Jabiri
PMOData and indicator updatesWeeklyNour Al-Jabiri
BeneficiariesWhat changes and whenAt each milestoneNour Al-Jabiri
Team memberRoleAllocation
Nour Al-JabiriProject manager⁦0%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Staff hours saved by HR automation0 hours / month3200 hours / monthMuhannad Al-Homsi
Paper and printing savings0 SYP million30 SYP millionRasha Al-Mudarres

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nour Al-JabiriDirector, Government Systems & IntegrationSubmitted—⁦2024-05-30⁩ 09:54
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2024-06-04⁩ 11:26
3Technical acceptance — project ownerTechnical acceptanceMuhannad Al-HomsiProject ownerApproved—⁦2024-06-05⁩ 12:33
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-06-09⁩ 10:49
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2024-06-10⁩ 11:26
6Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2024-06-11⁩ 09:54

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2024-06-04⁩

Technical acceptance — project owner

Muhannad Al-Homsi

Approved⁦2024-06-05⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2024-06-09⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2024-06-10⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2024-06-11⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Nour Al-Jabiri on ⁦2024-05-30⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-06-04⁩ at ⁦11:26⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Muhannad Al-Homsi · Project owner

    Approved · ⁦2024-06-05⁩ at ⁦12:33⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-06-09⁩ at ⁦10:49⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-06-10⁩ at ⁦11:26⁩

  5. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2024-06-11⁩ at ⁦09:54⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-05-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Nour Al-Jabiri

  2. V1Returned for edit⁦2024-05-16⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Nour Al-Jabiri