Government HR System — Employee Self-Service
Add to watchlistSelf-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.
Budget (BAC)
Actual cost
94% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
Self-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.
In scope
- Self-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.
- Migration from legacy systems
- ERP integration
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2024-05-30
Baseline approved at the planning gate
BudgetSYP285MFinish2025-09-30
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical2
- Regulatory1
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
100%
6/6 · test result is a pass
Accepted
100%
6/6 · signed off by the business owner
Display options
| REQ-032-01 | One system for the procedures | Business | Must | Completed | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | SB-1 | |
| REQ-032-02 | Historical data migration | Technical | Must | Completed | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | SB-1 | |
| REQ-032-03 | Ready operational reports | Functional | Must | Completed | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | SB-1 | |
| REQ-032-04 | ERP integration | Technical | Could | Completed | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | SB-1 | |
| REQ-032-05 | Data classification | Regulatory | Could | Completed | Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentP-019muhannad.alhomsi@psa.gov.sy | SB-1 | |
| REQ-032-06 | Identity and access management | Security | Should | Completed | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.