1.00Schedule performance index · 1.001.06Cost performance index · 1.06
Forecast finish
2025-09-21
On baseline
Closure·Stage 5 of 5
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
−9 days vs approved
Current forecast2025-09-21
Baseline (original = approved) · By earned schedule2025-09-30
Critical activities
0
of 0 open activities
Late activities
0
past their baseline finish
Schedule performance
1.00
earned ÷ planned value
Breached constraints
0
binding dates that will be missed
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2024
2025
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Today
2025-09-21100%
Government HR System — Employee Self-ServicePlanned: 2024-05-05 → 2025-09-30Actual: 2024-05-05 → 2025-09-21