PRJ-2026-032On track5ClosureAgileCompletedDelivered by:Ministry of Administrative Development

Government HR System — Employee Self-Service

Add to watchlist

Self-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.

Budget (BAC)

SYP 285M

Actual cost

SYP 268.9M

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 268.9M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP276.5M⁦16⁩ elements
Unallocated contingencySYP8.6MSYP 14.3M
Budget at completionSYP285MPRJ-2026-032
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project504⁦2024-05-05⁩⁦2025-09-21⁩⁦100%⁩276.45268.87—
1
Phase113⁦2024-05-05⁩⁦2024-08-26⁩⁦100%⁩22.1221.51—
1.1
WBS element70⁦2024-05-05⁩⁦2024-07-14⁩⁦100%⁩11.0610.750 / 1
1.2
WBS element70⁦2024-06-17⁩⁦2024-08-26⁩⁦100%⁩11.0610.751 / 2
2
Phase113⁦2024-07-31⁩⁦2024-11-21⁩⁦100%⁩47.0045.71—
2.1
WBS element69⁦2024-07-31⁩⁦2024-10-08⁩⁦100%⁩23.5022.851 / 1
2.2
WBS element70⁦2024-09-12⁩⁦2024-11-21⁩⁦100%⁩23.5022.851 / 2
3
Phase156⁦2024-10-26⁩⁦2025-03-31⁩⁦100%⁩110.58107.55—
3.1
WBS element69⁦2024-10-26⁩⁦2025-01-03⁩⁦100%⁩36.8635.851 / 1
3.2
WBS element70⁦2024-12-08⁩⁦2025-02-16⁩⁦100%⁩36.8635.851 / 1
3.3
WBS element69⁦2025-01-21⁩⁦2025-03-31⁩⁦100%⁩36.8635.851 / 2
4
Phase113⁦2025-03-05⁩⁦2025-06-26⁩⁦100%⁩55.2953.77—
4.1
WBS element70⁦2025-03-05⁩⁦2025-05-14⁩⁦100%⁩27.6526.891 / 1
4.2
WBS element69⁦2025-04-18⁩⁦2025-06-26⁩⁦100%⁩27.6526.891 / 2
5
Phase113⁦2025-05-31⁩⁦2025-09-21⁩⁦100%⁩41.4740.33—
5.1
WBS element70⁦2025-05-31⁩⁦2025-08-09⁩⁦100%⁩20.7320.171 / 1
5.2
WBS element70⁦2025-07-13⁩⁦2025-09-21⁩⁦100%⁩20.7320.171 / 1
Total⁦100%⁩276.45268.87