PRJ-2026-032On track5ClosureAgileCompletedDelivered by:Ministry of Administrative Development
Government HR System — Employee Self-Service
Add to watchlistSelf-service for public employees — leave, pay details, certificates and administrative requests — within the government HR system.
Project managerNour Al-JabiriProject sponsorSalma Al-ZaimProgrammeIntegrated Government Systems Programme
Budget (BAC)
SYP 285M
Actual cost
SYP 268.9M
94% of budget
Progress
100%Awaiting acceptance 0%
Estimate at completion
SYP 268.9M
SPI · CPI
1.00Schedule performance index · 1.001.06Cost performance index · 1.06
Forecast finish
2025-09-21
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to workSYP276.5M16 elements
Unallocated contingencySYP8.6MSYP 14.3M
Budget at completionSYP285MPRJ-2026-032
Weighted progress100%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Total100%276.45268.87