Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-028On track4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

Preparing the 2026–2028 Medium-Term Plan & Governorate Plans

Add to watchlist

Preparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.

Budget (BAC)

SYP 80M

Actual cost

SYP 56M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 80M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+4

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦70% done against 68% planned⁩.

⁦SPI 1⁩.⁦03⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Balanced Local Development across the GovernoratesSO-6.2Governorate plans and a balanced share of public investment

Main initiative

SI-5.2.2Performance measurement, monitoring & evaluation

Contribution to the initiative⁦19%⁩

The project’s share of the initiative’s project budget (3 projects)

Annual work-plan line
WP-2026-028
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦70%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦19%⁩

6 deliverables accepted

  • Target model⁦17%⁩
  • Roadmap⁦17%⁩
  • Current-state assessment⁦12%⁩
  • Benchmarking⁦12%⁩
  • Project plan & baseline⁦6%⁩
  • Monitoring & reporting⁦6%⁩

1 deliverable under inspection or acceptance

  • Wave 1⁦11%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦94%⁩ of budget

SYP56M/ SYP80M
Actual spend
SYP56M
Committed
SYP75M
Approved budget
SYP80M
Estimate at completion
SYP80M

Next milestones

  • Provisional acceptance⁦2026-11-27⁩On track
  • Closure⁦2026-12-15⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

0 open risks, exposure SYP 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦10⁩ approved

  • Project plan & baseline028-D1 · V1 · CRT-028-01⁦6%⁩Rana Al-Samman2026-06-062026-06-06Approved
  • Monitoring & reporting028-D2 · V1 · CRT-028-02⁦6%⁩Dr. Mais Al-Sibai2026-06-272026-06-27Approved
  • Current-state assessment028-D3 · V1 · CRT-028-03⁦12%⁩Dr. Mais Al-Sibai2026-07-192026-07-19Approved
  • Benchmarking028-D4 · V1 · CRT-028-04⁦12%⁩Dr. Ziad Al-Atassi2026-08-092026-08-09Approved
  • Target model028-D5 · V1 · CRT-028-05⁦17%⁩Dr. Ziad Al-Atassi2026-08-302026-08-30Approved
  • Roadmap028-D6 · V1 · CRT-028-06⁦17%⁩Rana Al-Samman2026-09-212026-09-21Approved
  • Wave 1028-D7 · V1⁦11%⁩Rana Al-Samman16 days overdue2026-10-12In review
  • Wave 2028-D8 · V0⁦11%⁩Dr. Mais Al-SibaiIn 5 days2026-11-02Draft
  • Knowledge transfer028-D9 · V0⁦4%⁩Dr. Mais Al-SibaiIn 27 days2026-11-24Draft
  • Final report028-D10 · V0⁦4%⁩Dr. Ziad Al-AtassiIn 48 days2026-12-15Draft

Team, contracts & documents

Team

3 members

Rana Al-Samman · Head of National StrategyDr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceDr. Reem Al-Qabbani · Director, National Project Management Office
  • Rana Al-SammanRana Al-SammanHead of National StrategyProject managerP-039rana.alsamman@psa.gov.sy⁦70%⁩
  • Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceProject sponsorP-009ziad.alatassi@psa.gov.sy⁦25%⁩
  • Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeGovernance adviser to the governorate plansP-002reem.alqabbani@psa.gov.sy⁦10%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close