PRJ-2026-028On track4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

Preparing the 2026–2028 Medium-Term Plan & Governorate Plans

Add to watchlist

Preparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.

Budget (BAC)

SYP 80M

Actual cost

SYP 56M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 80M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP77.6M⁦15⁩ elements
Unallocated contingencySYP2.4MSYP 4M
Budget at completionSYP80MPRJ-2026-028
Weighted progress⁦70%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project226⁦2026-05-03⁩⁦2026-12-15⁩⁦70%⁩77.6056.00—
1
Phase70⁦2026-05-03⁩⁦2026-07-12⁩⁦100%⁩7.767.99—
1.1
WBS element43⁦2026-05-03⁩⁦2026-06-15⁩⁦100%⁩3.884.000 / 1
1.2
WBS element43⁦2026-05-30⁩⁦2026-07-12⁩⁦100%⁩3.884.001 / 2
2
Phase70⁦2026-06-26⁩⁦2026-09-04⁩⁦100%⁩15.5215.99—
2.1
WBS element43⁦2026-06-26⁩⁦2026-08-08⁩⁦100%⁩7.767.991 / 1
2.2
WBS element43⁦2026-07-23⁩⁦2026-09-04⁩⁦100%⁩7.767.991 / 2
3
Phase68⁦2026-08-19⁩⁦2026-10-26⁩⁦100%⁩23.2823.98—
3.1
WBS element43⁦2026-08-19⁩⁦2026-10-01⁩⁦100%⁩11.6411.991 / 1
3.2
WBS element41⁦2026-09-15⁩⁦2026-10-26⁩⁦100%⁩11.6411.991 / 2
4
Phase75⁦2026-09-08⁩⁦2026-11-22⁩⁦34%⁩23.288.03—
4.1
WBS element64⁦2026-09-08⁩⁦2026-11-11⁩⁦67%⁩11.648.031 / 1
4.2
WBS element18⁦2026-11-04⁩⁦2026-11-22⁩⁦0%⁩11.64—1 / 2
5
Phase30⁦2026-11-15⁩⁦2026-12-15⁩⁦0%⁩7.76——
5.1
WBS element18⁦2026-11-15⁩⁦2026-12-03⁩⁦0%⁩3.88—1 / 1
5.2
WBS element18⁦2026-11-26⁩⁦2026-12-14⁩⁦0%⁩3.88—1 / 1
Total⁦70%⁩77.6056.00