Preparing the 2026–2028 Medium-Term Plan & Governorate Plans
Add to watchlistPreparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-06-27 | 2026-07-12 | +15 days | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-08-09 | 2026-09-04 | +26 days | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-09-21 | 2026-10-26 | +35 days | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-02 | 2026-11-22 | +20 days | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-15 | 2026-12-15 | On time | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
70%Awaiting acceptance
11%Not handed in
19%Deliverable flow
Display options
| Project plan & baseline028-D1 | 6% | CRT-028-01 | Approved | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | Dr. Mais Al-Sibai | 2026-06-06 | V1 | 3 of 3 |
| Monitoring & reporting028-D2 | 6% | CRT-028-02 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-06-27 | V1 | 3 of 3 |
| Current-state assessment028-D3 | 12% | CRT-028-03 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-07-19 | V1 | 3 of 3 |
| Benchmarking028-D4 | 12% | CRT-028-04 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-08-09 | V1 | 3 of 3 |
| Target model028-D5 | 17% | CRT-028-05 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-08-30 | V1 | 3 of 3 |
| Roadmap028-D6 | 17% | CRT-028-06 | Approved | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | Dr. Mais Al-Sibai | 2026-09-21 | V1 | 3 of 3 |
| Wave 1028-D7 | 11% | — | Under review | Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy | Dr. Mais Al-Sibai | 2026-10-12 | V1 | 1 of 3 |
| Wave 2028-D8 | 11% | — | Draft | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-11-02 | V0 | 0 of 3 |
| Knowledge transfer028-D9 | 4% | — | Draft | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-11-24 | V0 | 0 of 3 |
| Final report028-D10 | 4% | — | Draft | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-12-15 | V0 | 0 of 3 |
| Total · 10 | 100% |