PRJ-2026-028On track4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

Preparing the 2026–2028 Medium-Term Plan & Governorate Plans

Add to watchlist

Preparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.

Budget (BAC)

SYP 80M

Actual cost

SYP 56M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 80M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-15⁩
    Budget
    SYP 80M
    ⁦15⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2026-05-03⁩ · by Dr. Ziad Al-Atassi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2026-12-15⁩
    Budget
    SYP 80M
    ⁦15⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Rana Al-Samman

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-15⁩⁦2026-12-15⁩

⁦0⁩ days

Budget

SYP 80MSYP 80M

⁦0.00⁩ SYP M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-072027-01
  • Project plan approved⁦+15⁩
  • Designs approved⁦+26⁩
  • Build complete⁦+35⁩
  • Testing & acceptance complete⁦+20⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+0.23⁩
  • 2Diagnosis⁦+0.47⁩
  • 3Design⁦+2.30⁩
  • 4Implementation⁦−0.14⁩
  • 5Handover & knowledge transfer⁦−0.07⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Rana Al-Samman
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2026-05-03⁩by Dr. Ziad Al-Atassi