Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-028On track4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

Preparing the 2026–2028 Medium-Term Plan & Governorate Plans

Add to watchlist

Preparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.

Budget (BAC)

SYP 80M

Actual cost

SYP 56M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 80M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-10-26⁩
ApprovedCRT-028-06Roadmap

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
Preparing the 2026–2028 Medium-Term Plan & Governorate Plans
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Strategy & National PMO Sector
Sponsor
Dr. Ziad Al-Atassi
Project manager
Rana Al-Samman

1The deliverableAuto-filled

DeliverableAuto-filled
Roadmap
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Rana Al-Samman
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦17%⁩
DueAuto-filled
⁦2026-09-21⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-028_3.2_v1.pdfV1Rana Al-Samman⁦2026-09-15⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Dr. Mais Al-Sibai
Accepted byAuto-filled
Dr. Ziad Al-Atassi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2026-003
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Rana Al-SammanHead of National StrategySubmitted—⁦2026-09-15⁩ 13:28
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-16⁩ 09:36
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Ziad Al-AtassiProject ownerOn behalf of Dr. Mais Al-SibaiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-09-20⁩ 10:43
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-09-22⁩ 10:43
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-09-23⁩ 11:20

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2026-09-16⁩

Inspection & technical acceptance — owner

Dr. Ziad Al-Atassi

Approved⁦2026-09-20⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2026-09-22⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2026-09-23⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Rana Al-Samman on ⁦2026-09-15⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-16⁩ at ⁦09:36⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Dr. Mais Al-Sibai · Project owner

    Approved · ⁦2026-09-20⁩ at ⁦10:43⁩ · On behalf of Dr. Mais Al-Sibai (Dr. Ziad Al-Atassi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-09-22⁩ at ⁦10:43⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-09-23⁩ at ⁦11:20⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-09-15⁩

    PRJ-2026-028_3.2_v1.pdf

    Rana Al-Samman

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close