PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

National Statistical Indicators & Open Data Portal

Add to watchlist

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

Budget (BAC)

SYP 537.5M

Actual cost

SYP 350.8M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 565.8M

+SYP 28.3M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
1On track
0At risk
2Late
Average delay78 days
Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-07-06⁩Forecast / actual: ⁦2026-11-13⁩Delay: 130 daysG3 +130
Executive
Project plan approvedPlanned: ⁦2025-11-26⁩Forecast / actual: ⁦2026-01-28⁩Delay: 63 daysG1 +63
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-16⁩Delay: 16 daysG5 +16
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-03⁩Forecast / actual: ⁦2026-12-15⁩Delay: 73 daysG4 +73
Project
Designs approvedPlanned: ⁦2026-02-23⁩Forecast / actual: ⁦2026-06-13⁩Delay: 110 daysG2 +110

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-11-26⁩⁦2026-01-28⁩⁦+63⁩ daysRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2026-02-23⁩⁦2026-06-13⁩⁦+110⁩ daysRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-07-06⁩⁦2026-11-13⁩⁦+130⁩ daysRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-10-03⁩⁦2026-12-15⁩⁦+73⁩ daysRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-16⁩⁦+16⁩ daysRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦62%⁩

Awaiting acceptance

⁦10%⁩

Not handed in

⁦28%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline016-D1⁦5%⁩CRT-016-01ApprovedRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syEng. Mustafa Al-Awa⁦2025-10-13⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting016-D2⁦5%⁩CRT-016-02ApprovedEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2025-11-26⁩V1⁦3⁩ of ⁦3⁩
Business requirements016-D3⁦10%⁩CRT-016-03ApprovedEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2026-01-10⁩V1⁦3⁩ of ⁦3⁩
Solution design016-D4⁦10%⁩CRT-016-04ApprovedEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syEng. Mustafa Al-Awa⁦2026-02-23⁩V1⁦3⁩ of ⁦3⁩
Release 1016-D5⁦16%⁩CRT-016-05ApprovedEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syEng. Mustafa Al-Awa⁦2026-04-09⁩V1⁦3⁩ of ⁦3⁩
Release 2016-D6⁦16%⁩CRT-016-06ApprovedRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syEng. Mustafa Al-Awa⁦2026-05-23⁩V1⁦3⁩ of ⁦3⁩
Integrations016-D7⁦10%⁩—Under reviewEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2026-07-06⁩V1⁦1⁩ of ⁦3⁩
System testing016-D8⁦8%⁩—DraftRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syEng. Mustafa Al-Awa⁦2026-08-20⁩V0⁦0⁩ of ⁦3⁩
User acceptance testing016-D9⁦8%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2026-10-03⁩V0⁦0⁩ of ⁦3⁩
Training & change016-D10⁦6%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2026-11-17⁩V0⁦0⁩ of ⁦3⁩
Go-live & handover016-D11⁦6%⁩—DraftEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syEng. Mustafa Al-Awa⁦2026-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩