Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
+SYP 28.3M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Finance & earned value
The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.
Budget anatomy
The approved SYP 537.5M split into spent, committed and left, with the estimate at completion
- Actual spendSYP 350.8M
- Committed, not spentSYP 59.2M
- Allotted, uncommittedSYP 111.4M
- Contingency availableSYP 16.1M
Budget
- EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
- SYP 537.5M
- Original budgetwhen the first baseline was approved
- SYP 537.5M
- Approved budgetafter approved change requests
- SYP 537.5M
- Current budgetavailable to spend now
- SYP 537.5M
- Revised budgetif the pending changes are approved
- SYP 537.5M
Commitments
- CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
- SYP 410M
- Contracts1 active contract
- SYP 355M
- Purchase orders2 orders
- SYP 55M
- Remaining budgetapproved less actual
- SYP 186.7M
Spend & outlook
- Actual costSyncedFrom the nightly finance-system syncincluding accruals
- SYP 350.8M
- Accrualswork done, not yet invoiced
- SYP 14M
- Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
- SYP 565.8M
- ContingencySYP 10.8M drawn of SYP 26.9M
- SYP 16.1M
Estimated vs approved budget
What the project proposal estimated before approval, against today’s approved budget and the estimate at completion
- Approved equals the estimate
- The estimate at completion is SYP 28.3M (5.3%) above the estimate
From the «project proposal & feasibility study» approved at the approval gate on 2025-05-20
ERP link — data readiness
The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system
- Cost centreCC-90016
- WBS elements5 elements · P-2026-016.01 …
- Purchase orders2 synced · 0 manual
- Invoices & certificates9 posted · 0 in approval
Where each figure comes from
- EstimatedManualFrom the project proposal — not from the finance system
- CommitmentsSyncedFrom the nightly finance-system sync
- Actual costSyncedFrom the nightly finance-system sync
- Estimate at completionManualThe project manager’s estimate — not from the finance system
Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.
Purchase-order registerManual edit log
Every manual update — who, when, why and from which source
No manual edits on this project
All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.
Budget bridge
From the original to the revised request
- Total
- Increase
- Decrease
Contingency draw-downs
SYP 10.8M drawn of SYP 26.9M
- Covering realised delivery risks2026-08-29SYP 10.8M
Purchase orders
- PO-2026-0905Test-environment servers and devicesSYP 29.3MSYP 13.2M paid
- PO-2025-0792Development and testing tool licencesSYP 25.7MSYP 25.7M paid
Cost breakdown structure
Every dimension adds up to the same totals
| Item | BudgetSYP M | CommittedSYP M | ActualSYP M | EACSYP M | VarianceSYP M | Consumption |
|---|---|---|---|---|---|---|
| 1Management & governance | 41.71 | 45.31 | 45.31 | 45.31 | −3.60 | |
| 2Analysis & design | 88.63 | 96.29 | 96.29 | 96.29 | −7.65 | |
| 3Build | 208.55 | 209.19 | 209.19 | 209.19 | −0.64 | |
| 4Testing & acceptance | 104.28 | 33.84 | 0.00 | 118.25 | −13.98 | |
| 5Launch & handover | 78.21 | 25.38 | 0.00 | 88.69 | −10.48 | |
| Unallocated contingency | 16.13 | 0.00 | 0.00 | 8.06 | +8.06 | |
| Total | 537.50 | 410.00 | 350.79 | 565.79 | −28.29 |
Budget split
WBS
SYP 537.5M
Budget
- Management & governanceSYP 41.7M8%
- Analysis & designSYP 88.6M16%
- BuildSYP 208.6M39%
- Testing & acceptanceSYP 104.3M19%
- Launch & handoverSYP 78.2M15%
- Unallocated contingencySYP 16.1M3%
Cash flow
Planned, committed, actual and forecast
Spend per period
SYP millions
- Planned
- Actual
- Forecast
Cumulative S-curve
Cumulative to close
- Actual, then forecast
- Planned, cumulative
- Committed, cumulative
- Forecast
Earned value management
At the data date 2026-10-28
Planned value, earned value and actual cost
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
0.64
Off track
Schedule performance index
SPI = EV ÷ PV
0.95
On track
Cost performance index
CPI = EV ÷ AC
Finish by earned schedule
2027-09-24+267
SPI(t) 0.66 against the approved finish 2026-12-31
- Planned valuePV
- SYP 516.9M
- The value of the work that should be done by today.
- PV
- Earned valueEV
- SYP 333.3M
- The value of the work actually done, at plan prices.
- EV = % complete × BAC
- Actual costAC
- SYP 350.8M
- What has actually been spent on the work done.
- AC
- Budget at completionBAC
- SYP 537.5M
- The approved budget for the whole project.
- BAC
- Cost varianceCV
- −17.54 SYP M
- Earned less actual; negative means paying more than the value.
- CV = EV − AC
- Schedule varianceSV
- −183.68 SYP M
- Earned less planned; negative means behind, in value.
- SV = EV − PV
- Cost performance indexCPI
- 0.95
- Value produced per pound spent; under 1 is an overrun.
- CPI = EV ÷ AC
- Schedule performance indexSPI
- 0.64
- Work done over work planned; under 1 is behind.
- SPI = EV ÷ PV
- Estimate at completionEAC
- SYP 565.8M
- What the project will cost when it finishes, as forecast.
- EAC = BAC ÷ CPI
- Estimate to completeETC
- SYP 215M
- What is still to be spent to completion.
- ETC = EAC − AC
- Variance at completionVAC
- −28.29 SYP M
- Budget less the estimate; negative is an overrun.
- VAC = BAC − EAC
- To-complete performance indexTCPI
- 1.09
- The cost efficiency the rest must reach to stay on budget.
- TCPI = (BAC − EV) ÷ (BAC − AC)
Automatic end-of-project forecast
Four ways to estimate the final cost, and the date earned schedule points to
- At today’s cost performanceSYP 565.8M
- If the rest goes to planSYP 555M
- At cost and schedule performanceSYP 684.3M
- The PM’s bottom-up estimateSYP 565.8M
- To stay within SYP 537.5M, cost performance on the rest must rise to 1.09 — above what has been achieved.
Estimate at completion at that performance
SYP 565.8M
Variance at completion: −28.29 SYP M