Original
Original baseline
- Finish
- 2026-12-31
- Budget
- SYP 537.5M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-08-03 · by Eng. Khaled Al-Kayyali
A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.
Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
+SYP 28.3M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-08-03 · by Eng. Khaled Al-Kayyali
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Razan Al-Rifai
What changed from version A to version B
Finish
2026-12-312027-01-16
+16 days
Budget
SYP 537.5MSYP 537.5M
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference