PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

National Statistical Indicators & Open Data Portal

Add to watchlist

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

Budget (BAC)

SYP 537.5M

Actual cost

SYP 350.8M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 565.8M

+SYP 28.3M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

National Statistical Indicators & Open Data Portal

APPROVEDV2Approved ⁦2025-08-01⁩

1Project identity

Required at this stage
Project name
National Statistical Indicators & Open Data Portal
Project code
PRJ-2026-016
Project sponsor
Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy
Project manager
Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy
Project owner
Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy
Portfolio & programme
Digital Government Services & Data PortfolioNational Data & Plan Follow-up Programme
Type & methodology
Digital · Waterfall
Current phase
4Execution

2Background & rationale

Required at this stage

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

3Objectives

Required at this stage
  1. 1Reliable statistics and economic data for decisions

4Scope

Required at this stage

In scope

  • A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Identity checks against the civil registry
  2. 2Integration with internal systems
  3. 3Accessibility and UX standards

6Deliverables

Required at this stage
1Project management plan⁦2025-08-24⁩
2Main deliverable — stage 1⁦2026-04-23⁩
3Main deliverable — final stage⁦2026-10-20⁩
4Final report⁦2026-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-08-01⁩
  2. Contract signed⁦2025-10-24⁩
  3. 50% of works complete⁦2026-04-23⁩
  4. Provisional acceptance⁦2026-11-20⁩
  5. Closure⁦2026-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.1%⁩SYP387.5M
  • Supervision & consulting⁦14.0%⁩SYP75M
  • Internal team⁦8.8%⁩SYP47.5M
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩SYP27.5M
The delivering body’s investment-plan allocationsTotalSYP537.5M

9Timeline

Required at this stage
Start
2025-08-033 August 2025
Baseline finish
2026-12-3131 December 2026
Duration
⁦17⁩ months

10Key risks

Required at this stage
  • MediumToo few accredited data owners in the ministries and governorates

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority