PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

National Statistical Indicators & Open Data Portal

Add to watchlist

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

Budget (BAC)

SYP 537.5M

Actual cost

SYP 350.8M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 565.8M

+SYP 28.3M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

In scope

  • A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-08-28⁩

    Baseline approved at the planning gate

    BudgetSYP537.5MFinish⁦2026-12-31⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional2
  • Technical1
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦17%⁩

1/6 · test result is a pass

Accepted

⁦17%⁩

1/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-016-01An end-to-end digital journey, no walk-inBusinessMustIn progressEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sySB-1
REQ-016-02Identity checks against the civil registryFunctionalMustIn progressRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sySB-1
REQ-016-03A user dashboardFunctionalMustApprovedEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sySB-1
REQ-016-04Integration with internal systemsTechnicalShouldIn progressRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sySB-1
REQ-016-05⁦WCAG 2⁩.⁦1⁩ accessibilityRegulatoryShouldIn progressEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sySB-1
REQ-016-06National cybersecurity controlsSecurityCouldIn progressRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sySB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.