PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority
National Statistical Indicators & Open Data Portal
Add to watchlist
A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.
0.89Schedule performance index · 0.890.95Cost performance index · 0.95
Forecast finish
2027-01-18
18 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure20 November 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+16 days vs approved
Baseline (original = approved)2026-12-31
Current forecast2027-01-16
By earned schedule2027-09-24
Critical activities
6
of 8 open activities
Late activities
5
past their baseline finish
Schedule performance
0.64
earned ÷ planned value
Next milestone
in 16 days
Build complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
Today
2027-01-1662%
National Statistical Indicators & Open Data PortalPlanned: 2025-08-03 → 2026-12-31Forecast: 2025-08-03 → 2027-01-16Float: 0d