PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

National Statistical Indicators & Open Data Portal

Add to watchlist

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

Budget (BAC)

SYP 537.5M

Actual cost

SYP 350.8M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 565.8M

+SYP 28.3M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-10-26⁩
ApprovedCRT-016-06Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-016
Project
National Statistical Indicators & Open Data Portal
Portfolio
Digital Government Services & Data Portfolio
Sector
Statistics Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Razan Al-Rifai

1The deliverableAuto-filled

DeliverableAuto-filled
Release 2
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Razan Al-Rifai
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦16%⁩
DueAuto-filled
⁦2026-05-23⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-016_3.2_v1.pdfV1Razan Al-Rifai⁦2026-07-11⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Mustafa Al-Awa
Accepted byAuto-filled
Eng. Khaled Al-Kayyali
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2025-017
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Razan Al-RifaiDirector, Data & AISubmitted—⁦2026-07-11⁩ 10:07
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-07-13⁩ 12:57
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Khaled Al-KayyaliProject ownerOn behalf of Eng. Mustafa Al-AwaApprovedInspected and accepted against the approved acceptance criteria.⁦2026-07-15⁩ 13:04
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-07-16⁩ 11:14
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-07-20⁩ 12:51

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2026-07-13⁩

Inspection & technical acceptance — owner

Eng. Khaled Al-Kayyali

Approved⁦2026-07-15⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2026-07-16⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2026-07-20⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Razan Al-Rifai on ⁦2026-07-11⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-07-13⁩ at ⁦12:57⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Mustafa Al-Awa · Project owner

    Approved · ⁦2026-07-15⁩ at ⁦13:04⁩ · On behalf of Eng. Mustafa Al-Awa (Eng. Khaled Al-Kayyali)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-07-16⁩ at ⁦11:14⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-07-20⁩ at ⁦12:51⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-07-11⁩

    PRJ-2026-016_3.2_v1.pdf

    Razan Al-Rifai

Only one version so far.