Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-005On track4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Network Cybersecurity Programme

Add to watchlist

A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.

Budget (BAC)

SYP 965M

Actual cost

SYP 824.5M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 936.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+1

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦88% done against 86% planned⁩.

⁦SPI 1⁩.⁦02⁩, ⁦CPI 1⁩.⁦03⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.2Sound governance and effective follow-up of projects and data

Main initiative

SI-5.2.1Government cloud & cybersecurity

Contribution to the initiative⁦16%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-005
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦88%⁩

Awaiting acceptance ⁦6%⁩

Not handed in ⁦6%⁩

9 deliverables accepted

  • Release 1⁦14%⁩
  • Release 2⁦14%⁩
  • Integrations⁦14%⁩
  • System testing⁦10%⁩
  • User acceptance testing⁦10%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦9%⁩
  • Project plan & baseline⁦4%⁩

1 deliverable under inspection or acceptance

  • Training & change⁦6%⁩

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦91%⁩ of budget

SYP824.5M/ SYP965MSYP28.1Mprojected saving(⁦2.9%⁩)
Actual spend
SYP824.5M
Committed
SYP880M
Approved budget
SYP965M
Estimate at completion
SYP936.9M

Next milestones

  • Closure⁦2026-12-10⁩was ⁦2026-12-15⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SYP 75M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩1Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩RSK-0042Undetected gaps in old ministry systems before they join the SOC
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦9⁩ of ⁦11⁩ approved

  • Project plan & baseline005-D1 · V1 · CRT-005-01⁦4%⁩Eng. Hussam Zeidan2025-05-072025-05-07Approved
  • Monitoring & reporting005-D2 · V1 · CRT-005-02⁦4%⁩Eng. Mazen Kassab2025-07-052025-07-05Approved
  • Business requirements005-D3 · V1 · CRT-005-03⁦9%⁩Eng. Mazen Kassab2025-09-012025-09-01Approved
  • Solution design005-D4 · V1 · CRT-005-04⁦9%⁩Eng. Khaled Al-Kayyali2025-10-302025-10-30Approved
  • Release 1005-D5 · V1 · CRT-005-05⁦14%⁩Eng. Khaled Al-Kayyali2025-12-282025-12-28Approved
  • Release 2005-D6 · V1 · CRT-005-06⁦14%⁩Eng. Hussam Zeidan2026-02-242026-02-24Approved
  • Integrations005-D7 · V1 · CRT-005-07⁦14%⁩Eng. Mazen Kassab2026-04-242026-04-24Approved
  • System testing005-D8 · V1 · CRT-005-08⁦10%⁩Eng. Hussam Zeidan2026-06-222026-06-22Approved
  • User acceptance testing005-D9 · V1 · CRT-005-09⁦10%⁩Eng. Mazen Kassab2026-08-202026-08-20Approved
  • Training & change005-D10 · V1⁦6%⁩Eng. Mazen Kassab11 days overdue2026-10-17Submitted
  • Go-live & handover005-D11 · V0⁦6%⁩Eng. Khaled Al-KayyaliIn 48 days2026-12-15Draft

Team, contracts & documents

Team

2 members

Eng. Hussam Zeidan · Director, CybersecurityEng. Dima Al-Dabbagh · Munjaz Platform Administrator
  • Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityProject managerP-026hussam.zeidan@psa.gov.sy⁦50%⁩
  • Eng. Dima Al-DabbaghEng. Dima Al-DabbaghMunjaz Platform AdministratorPlatform engineer, cybersecurity programmeP-008dima.aldabbagh@psa.gov.sy⁦20%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close