National cybersecurity controls compliance — Q3

RestrictedApprovedV1

The quarterly national cybersecurity controls compliance report sent to the Ministry of Communications and Information Technology.

More

Restricted

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0222
Version
V1
Date
2026-10-09

National cybersecurity controls compliance — ⁦Q3⁩

Government Network Cybersecurity Programme

⁦1⁩. Executive summary

This report gives the position of Government Network Cybersecurity Programme to date: ⁦88% complete against 86% planned⁩, ⁦SPI 1⁩.⁦02⁩, ⁦CPI 1⁩.⁦03⁩, and an estimate at completion of SYP ⁦937M⁩.

Project
Government Network Cybersecurity Programme (⁦PRJ-2026-005⁩)
Project manager
Eng. Hussam Zeidan
Budget
SYP ⁦965M⁩
Progress
⁦88% actual against 86% planned⁩
Forecast finish
⁦2026-12-10⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Eng. Hussam Zeidan
Issued from Munjaz — valid only once approved electronically1 / 1