PRJ-2026-005On track4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Network Cybersecurity Programme

Add to watchlist

A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.

Budget (BAC)

SYP 965M

Actual cost

SYP 824.5M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 936.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
1On track
0At risk
0Late
Average delay38 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-04-24⁩Forecast / actual: ⁦2026-06-18⁩Delay: 55 daysG3 +55
Executive
Project plan approvedPlanned: ⁦2025-07-05⁩Forecast / actual: ⁦2025-07-23⁩Delay: 18 daysG1 +18
Payment
Final handoverPlanned: ⁦2026-12-15⁩Forecast / actual: ⁦2027-01-02⁩Delay: 18 daysG5 +18
Regulatory
Testing & acceptance completePlanned: ⁦2026-08-20⁩Forecast / actual: ⁦2026-10-26⁩Delay: 67 daysG4 +67
Project
Designs approvedPlanned: ⁦2025-10-30⁩Forecast / actual: ⁦2025-12-02⁩Delay: 33 daysG2 +33

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-07-05⁩⁦2025-07-23⁩⁦+18⁩ daysEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-10-30⁩⁦2025-12-02⁩⁦+33⁩ daysEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-04-24⁩⁦2026-06-18⁩⁦+55⁩ daysEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-08-20⁩⁦2026-10-26⁩⁦+67⁩ daysEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syAchieved1Approved
Final handoverMS-G5Payment⁦2026-12-15⁩⁦2027-01-02⁩⁦+18⁩ daysEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦88%⁩

Awaiting acceptance

⁦6%⁩

Not handed in

⁦6%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline005-D1⁦4%⁩CRT-005-01ApprovedEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syEng. Mazen Kassab⁦2025-05-07⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting005-D2⁦4%⁩CRT-005-02ApprovedEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.syEng. Mazen Kassab⁦2025-07-05⁩V1⁦3⁩ of ⁦3⁩
Business requirements005-D3⁦9%⁩CRT-005-03ApprovedEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.syEng. Mazen Kassab⁦2025-09-01⁩V1⁦3⁩ of ⁦3⁩
Solution design005-D4⁦9%⁩CRT-005-04ApprovedEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syEng. Mazen Kassab⁦2025-10-30⁩V1⁦3⁩ of ⁦3⁩
Release 1005-D5⁦14%⁩CRT-005-05ApprovedEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syEng. Mazen Kassab⁦2025-12-28⁩V1⁦3⁩ of ⁦3⁩
Release 2005-D6⁦14%⁩CRT-005-06ApprovedEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syEng. Mazen Kassab⁦2026-02-24⁩V1⁦3⁩ of ⁦3⁩
Integrations005-D7⁦14%⁩CRT-005-07ApprovedEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.syEng. Mazen Kassab⁦2026-04-24⁩V1⁦3⁩ of ⁦3⁩
System testing005-D8⁦10%⁩CRT-005-08ApprovedEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syEng. Mazen Kassab⁦2026-06-22⁩V1⁦3⁩ of ⁦3⁩
User acceptance testing005-D9⁦10%⁩CRT-005-09ApprovedEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.syEng. Mazen Kassab⁦2026-08-20⁩V1⁦3⁩ of ⁦3⁩
Training & change005-D10⁦6%⁩—SubmittedEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.syEng. Mazen Kassab⁦2026-10-17⁩V1⁦1⁩ of ⁦3⁩
Go-live & handover005-D11⁦6%⁩—DraftEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syEng. Mazen Kassab⁦2026-12-15⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩