Execution
Deliverable completion certificate
Evidence, inspection, acceptance and the financial link
- Form no.
- PSA-PMO-F08
- Template edition
- 1.1
- Version
- V1
- Form date
- 2026-08-23
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-005
- Project
- Government Network Cybersecurity Programme
- Portfolio
- Government Digital Infrastructure & Systems Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Eng. Khaled Al-Kayyali
- Project manager
- Eng. Hussam Zeidan
1The deliverableAuto-filled
- DeliverableAuto-filled
- System testing
- DescriptionAuto-filled
- A contractual output tied to its WBS work package.
- OwnerAuto-filled
- Eng. Hussam Zeidan
- VersionAuto-filled
- V1
- Weight in the projectAuto-filled
- 10%
- DueAuto-filled
- 2026-06-22
2Evidence of completionAuto-filled
| File | Version | By | Date |
|---|---|---|---|
| PRJ-2026-005_4.1_v1.pdf | V1 | Eng. Hussam Zeidan | 2026-05-09 |
3Inspection and acceptance criteria
| Criterion | Result |
|---|---|
| Matches the approved scope of work | Met |
| Quality review with no major findings | Met |
| Evidence attached and signed by the owner | Met |
| Met | 3 of 3 |
- InspectorAuto-filled
- Eng. Mazen Kassab
- Accepted byAuto-filled
- Eng. Khaled Al-Kayyali
- Acceptance note
- Inspected and accepted against the approved acceptance criteria.
4Financial linkAuto-filled
- Contract milestoneAuto-filled
- Testing & acceptance complete
- ContractAuto-filled
- CTR-2025-004
- Payment certificateAuto-filled
- Linked when the certificate is raised
- Payment against itAuto-filled
- —
Approval logChain: Deliverable acceptance & certificate · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Hussam ZeidanDirector, Cybersecurity | Submitted | — | 2026-05-09 10:37 |
| 2 | Evidence against the acceptance criteria | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-05-11 10:31 |
| 3 | Inspection & technical acceptance — owner | Technical acceptance | Eng. Khaled Al-KayyaliProject ownerOn behalf of Eng. Mazen Kassab | Approved | Inspected and accepted against the approved acceptance criteria. | 2026-05-14 11:38 |
| 4 | Deliverable matched to the contract line | Financial approval | Abdullah Al-UjailiProcurement & contracts | Approved | — | 2026-05-17 09:24 |
| 5 | Certificate linked to the payment certificate | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2026-05-19 10:01 |
Signatures
Evidence against the acceptance criteria
Mariam Al-Zoubi
Approved2026-05-11
Inspection & technical acceptance — owner
Eng. Khaled Al-Kayyali
Approved2026-05-14
Deliverable matched to the contract line
Abdullah Al-Ujaili
Approved2026-05-17
Certificate linked to the payment certificate
Rasha Al-Mudarres
Approved2026-05-19