Original
Original baseline
- Finish
- 2026-12-15
- Budget
- SYP 965M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-02-02 · by Eng. Khaled Al-Kayyali
A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.
Budget (BAC)
Actual cost
85% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure22 October 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-02-02 · by Eng. Khaled Al-Kayyali
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Hussam Zeidan
What changed from version A to version B
Finish
2026-12-152027-01-02
+18 days
Budget
SYP 965MSYP 965M
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference