PRJ-2026-005On track4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Network Cybersecurity Programme

Add to watchlist

A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.

Budget (BAC)

SYP 965M

Actual cost

SYP 824.5M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 936.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.

In scope

  • A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-03-07⁩

    Baseline approved at the planning gate

    BudgetSYP965MFinish⁦2026-12-15⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical2
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦50%⁩

3/6 · test result is a pass

Accepted

⁦50%⁩

3/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-005-01One system for the proceduresBusinessMustIn progressEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sySB-1
REQ-005-02Historical data migrationTechnicalMustIn progressEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sySB-1
REQ-005-03Ready operational reportsFunctionalMustIn progressEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sySB-1
REQ-005-04ERP integrationTechnicalCouldApprovedEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sySB-1
REQ-005-05Data classificationRegulatoryCouldApprovedEng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sySB-1
REQ-005-06Identity and access managementSecurityShouldIn progressEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sySB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.