Civil Registry Automation & Governorate Link-up
Add to watchlistDigitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.
Budget (BAC)
Actual cost
6% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution30 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-11-04 | 2026-12-04 | +30 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-02-05 | 2027-03-02 | +25 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-06-26 | 2027-07-12 | +16 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-09-27 | 2027-10-08 | +11 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-30 | 2028-01-04 | +5 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
6%Awaiting acceptance
4%Not handed in
90%Deliverable flow
Display options
| Project plan & baseline011-D1 | 6% | CRT-011-01 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Ibrahim Al-Saeed | 2026-09-18 | V1 | 3 of 3 |
| Monitoring & reporting011-D2 | 4% | — | Submitted | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2026-11-04 | V1 | 1 of 3 |
| Business requirements011-D3 | 8% | — | Draft | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2026-12-21 | V0 | 0 of 3 |
| Solution design011-D4 | 8% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2027-02-05 | V0 | 0 of 3 |
| Release 1011-D5 | 13% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2027-03-24 | V0 | 0 of 3 |
| Release 2011-D6 | 13% | — | Draft | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Ibrahim Al-Saeed | 2027-05-10 | V0 | 0 of 3 |
| Integrations011-D7 | 13% | — | Draft | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2027-06-26 | V0 | 0 of 3 |
| System testing011-D8 | 10% | — | Draft | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Ibrahim Al-Saeed | 2027-08-12 | V0 | 0 of 3 |
| User acceptance testing011-D9 | 10% | — | Draft | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2027-09-27 | V0 | 0 of 3 |
| Training & change011-D10 | 8% | — | Draft | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2027-11-13 | V0 | 0 of 3 |
| Go-live & handover011-D11 | 7% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2027-12-30 | V0 | 0 of 3 |
| Total · 11 | 100% |