Planning
Project management plan
Schedule, deliverables, risks, communications, quality and benefits
- Form no.
- PSA-PMO-F05
- Template edition
- 2.0
- Version
- V1
- Form date
- 2026-07-30
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-011
- Project
- Civil Registry Automation & Governorate Link-up
- Portfolio
- Government Digital Infrastructure & Systems Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Eng. Bashir Al-Tai
- Project manager
- Nour Al-Jabiri
1ScheduleAuto-filled
From the project schedule and its approved baseline.
Start
2026-07-05
Baseline finish
2027-12-30
Forecast finish
2027-12-30
SPI
1.00
| Milestone | Planned | Forecast | Slip |
|---|---|---|---|
| Project plan approved | 2026-11-04 | 2026-12-04 | +30 days |
| Designs approved | 2027-02-05 | 2027-03-02 | +25 days |
| Build complete | 2027-06-26 | 2027-07-12 | +16 days |
| Testing & acceptance complete | 2027-09-27 | 2027-10-08 | +11 days |
| Final handover | 2027-12-30 | 2028-01-04 | +5 days |
2DeliverablesAuto-filled
| Deliverable | Weight | Due | Owner |
|---|---|---|---|
| Project plan & baseline | 6% | 2026-09-18 | Nour Al-Jabiri |
| Monitoring & reporting | 4% | 2026-11-04 | Ibrahim Al-Saeed |
| Business requirements | 8% | 2026-12-21 | Ibrahim Al-Saeed |
| Solution design | 8% | 2027-02-05 | Eng. Bashir Al-Tai |
| Release 1 | 13% | 2027-03-24 | Eng. Bashir Al-Tai |
| Release 2 | 13% | 2027-05-10 | Nour Al-Jabiri |
| Integrations | 13% | 2027-06-26 | Ibrahim Al-Saeed |
| System testing | 10% | 2027-08-12 | Nour Al-Jabiri |
| User acceptance testing | 10% | 2027-09-27 | Ibrahim Al-Saeed |
| Training & change | 8% | 2027-11-13 | Ibrahim Al-Saeed |
| Go-live & handover | 7% | 2027-12-30 | Eng. Bashir Al-Tai |
| Accepted with a certificate | 6% | — | — |
3RisksAuto-filled
| Code | Risk | Score | Response | Owner |
|---|---|---|---|---|
| No risks recorded | ||||
4CommunicationsAuto-filled
| Audience | Need | Frequency | Owner |
|---|---|---|---|
| Project sponsor | Status and decisions needed | Monthly | Nour Al-Jabiri |
| Project owner | Deliverable status and acceptance dates | Fortnightly | Nour Al-Jabiri |
| PMO | Data and indicator updates | Weekly | Nour Al-Jabiri |
| Beneficiaries | What changes and when | At each milestone | Nour Al-Jabiri |
| Team member | Role | Allocation |
|---|---|---|
| Nour Al-Jabiri | Project manager | 20% |
| Eng. Nadine Ismail | Integration adviser, civil registry to the unified platform | 35% |
| Eng. Rita Ghanem | Civil registry architecture & Interior Ministry / governorate links | 30% |
5QualityAuto-filled
- Peer review of every deliverable before acceptance
- Written acceptance criteria for every deliverable
- A PMO audit at every gate
6BenefitsAuto-filled
| Benefit | Baseline | Target | Owner |
|---|---|---|---|
| No benefits recorded | |||
Approval logChain: Project management plan approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Nour Al-JabiriDirector, Government Systems & Integration | Submitted | — | 2026-10-23 12:33 |
| 2 | Methodology review — PMO | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-10-27 14:35 |
Signatures
Methodology review — PMO
Mariam Al-Zoubi
Approved2026-10-27
Technical acceptance — project owner
Ibrahim Al-Saeed
Awaiting decision
Cash flow & financial commitment
Rasha Al-Mudarres
Later
Sponsor approval
Eng. Bashir Al-Tai
Later