Civil Registry Automation & Governorate Link-up

Add to watchlist

Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.

Budget (BAC)

SYP 600M

Actual cost

SYP 36M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SYP 600M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Civil Registry Automation & Governorate Link-up

APPROVEDV2Approved ⁦2026-07-03⁩

1Project identity

Required at this stage
Project name
Civil Registry Automation & Governorate Link-up
Project code
PRJ-2026-011
Project sponsor
Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy
Project manager
Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy
Project owner
Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy
Portfolio & programme
Government Digital Infrastructure & Systems PortfolioIntegrated Government Systems Programme
Type & methodology
IT · Waterfall
Current phase
3Planning

2Background & rationale

Required at this stage

Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.

3Objectives

Required at this stage
  1. 1Integrated digital government services for citizens
  2. 2Comparable public-service quality in every governorate

4Scope

Required at this stage

In scope

  • Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3National cybersecurity controls

6Deliverables

Required at this stage
1Project management plan⁦2026-07-27⁩
2Main deliverable — stage 1⁦2027-04-08⁩
3Main deliverable — final stage⁦2027-10-15⁩
4Final report⁦2027-12-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-07-03⁩
  2. Contract signed⁦2026-09-30⁩
  3. 50% of works complete⁦2027-04-08⁩
  4. Provisional acceptance⁦2027-11-17⁩
  5. Closure⁦2027-12-30⁩

8Budget

Required at this stage
  • Main contract⁦72.1%⁩SYP432.5M
  • Supervision & consulting⁦13.8%⁩SYP82.5M
  • Internal team⁦9.2%⁩SYP55M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP30M
The delivering body’s investment-plan allocationsTotalSYP600M

9Timeline

Required at this stage
Start
2026-07-055 July 2026
Baseline finish
2027-12-3030 December 2027
Duration
⁦18⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly