PRJ-2026-011On track3PlanningWaterfallNot startedDelivered by:Ministry of Interior

Civil Registry Automation & Governorate Link-up

Add to watchlist

Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.

Budget (BAC)

SYP 600M

Actual cost

SYP 36M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SYP 600M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2026-07-03⁩
ApprovedPRJ-2026-011Civil Registry Automation & Governorate Link-up

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-011
Project
Civil Registry Automation & Governorate Link-up
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Nour Al-Jabiri

1Objective

Background

Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.

Project objectives

  1. Integrated digital government services for citizens
  2. Comparable public-service quality in every governorate

2Scope

In scope

  • Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2026-07-27⁩
Main deliverable — stage 1⁦2027-04-08⁩
Main deliverable — final stage⁦2027-10-15⁩
Final report⁦2027-12-30⁩
MilestoneDate
Charter approved⁦2026-07-03⁩
Contract signed⁦2026-09-30⁩
50% of works complete⁦2027-04-08⁩
Provisional acceptance⁦2027-11-17⁩
Closure⁦2027-12-30⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Bashir Al-Tai
Project ownerAuto-filled
Ibrahim Al-Saeed
Project managerAuto-filled
Nour Al-Jabiri
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 432.5M
Supervision & consultingSYP 82.5M
Internal teamSYP 55M
Contingency reserve (5%)SYP 30M
Approved budgetSYP 600M

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nour Al-JabiriDirector, Government Systems & IntegrationSubmitted—⁦2026-06-24⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2026-06-27⁩ 12:30
3Project ownerTechnical acceptanceIbrahim Al-SaeedProject ownerApproved—⁦2026-06-30⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-07-01⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Bashir Al-TaiProject sponsorApproved—⁦2026-07-03⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2026-06-27⁩

Project owner

Ibrahim Al-Saeed

Approved⁦2026-06-30⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2026-07-01⁩

Sponsor approval

Eng. Bashir Al-Tai

Approved⁦2026-07-03⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Nour Al-Jabiri on ⁦2026-06-24⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2026-06-27⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2026-06-30⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-07-01⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Bashir Al-Tai · Project sponsor

    Approved · ⁦2026-07-03⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-07-03⁩

    Approved version

    • PMO comments addressed