SO-2.1 · Rehabilitate core energy, water and transport infrastructure

National connectivity & support services

At riskDelivered wholly through projectsReconstruction & Infrastructure

Smart lighting and signals on the Damascus–Daraa highway, the government fibre backbone between Damascus and Homs, census preparation, and the unified government contact centre with the AI assistant.

⁦54%⁩

Initiative weighted progress

⁦54.1%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦54.1%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

SYP9.1B

4 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

PRJ-2026-013

Primary⁦30%⁩⁦79%⁩⁦23.7%⁩
Government Fibre Backbone — Damascus–Homs Segment

PRJ-2026-018

Primary⁦35%⁩⁦55%⁩⁦19.3%⁩
Population & Housing Census Preparation — Phase 1

PRJ-2026-022

Primary⁦15%⁩⁦2%⁩⁦0.3%⁩
Unified Government Contact Centre & AI Assistant

PRJ-2026-024Left out — proposed

Primary⁦20%⁩⁦0%⁩—

Linked projects’ progress

Σ (contribution × progress) = ⁦43.3%⁩ points ÷ shares counted ⁦80%⁩ = ⁦54.1%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦54.1%⁩

A proposed or cancelled project, or one with no approved share, is left out; a suspended one follows the rule set on the project weight model.

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

Smart lighting and signals on the Damascus–Daraa highway, the government fibre backbone between Damascus and Homs, census preparation, and the unified government contact centre with the AI assistant.

Outputs

  • 1,200 lighting poles and cameras on the southern highway
  • The Damascus–Homs government backbone
  • Maps and tablets for the census field offices
  • The unified government contact centre

Delivery phases

  • Lighting and backbone

    2025-02-16 — 2027-03-05

  • Census preparation

    2026-08-02 — 2028-03-31

  • Contact centre & AI assistant

    2027-01-03 — 2028-12-31

Today · 2026-10-28

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

No benefits registered for these projects yet; they are recorded at closure and handover.

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: Government Fibre Backbone — Damascus–Homs Segment

1Deliverable weight in the project

⁦38.0%⁩

Weight of «Civil works» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦11.3%⁩

Its relative weight in Reconstruction & Infrastructure Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦35%⁩

Its contribution to «National connectivity & support services»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Possible riskMediumOpen

    The contact-centre project is not yet in the 2027 investment plan

    Response: Put it to the 2027 annual work plan approval

    Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy

Deviation

Budget: projects total SYP 9.1B against the estimate SYP 9.3B

Schedule: last project ends ⁦2028-12-31⁩ against the initiative end ⁦2028-12-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.