Copilot read the reports, delays, correspondence, impediments and change requests and suggests what the register does not cover. Accept to open the risk form already filled, or dismiss with a reason.
AI insight
User acceptance testing with the service-centre staff cannot start on time (2026-12-01)
Unified Government e-Services Platform16HighSYP 40MThe civil-registry test environment has been down 9 days, automated coverage is under 60% and the phased test plan is late — three signals converge on one milestone no risk covers
A late substation 4 commissioning holds up practical training at the technical engineering faculty
Latakia University Technical Engineering Faculty Extension12MediumSYP 57.5MThe Aleppo substations are 126 days late and the technical engineering faculty needs substation 4 as a training site from 2026-12-31 — the delay exceeds the float by 34 days
The contractor may suspend works over unpaid variations
Hama National Hospital Upgrade & Extension15HighSYP 300MA claim on variation 7 since September, a delay-penalty warning and a legal opinion on going to dispute resolution — a pattern that usually precedes a suspension notice
Financial data migration pushes go-live past the fiscal year-end close
Integrated Public Financial Management System — Phase 112MediumSYP 85MAsset data is unavailable, the ministries’ payroll link failed twice and the allocation increase is still in review — a December go-live collides with the year-end close
Reuse the platform’s civil-registry integration in the mobile app instead of rebuilding it
Government Services Mobile App — New Release9OpportunitySYP 16MThe app plans its own civil-registry integration while the unified platform builds the same interface — sharing saves about four weeks
Late delivery of operating-theatre equipment from the overseas supplier
Hama National Hospital Upgrade & Extension
Schedule
16High
SYP 375M
Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022·sara.albarazi@psa.gov.sy
Mitigate
Open
In 48 days2026-12-15
3 d
RSK-0036Material
City council late clearing rubble and opening access roads to the work sites
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Financial
16High
SYP 350M
Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016·firas.alobaid@psa.gov.sy
Mitigate
Open
In 64 days2026-12-31
56 d
RSK-0043Material
Allocation left out of the 2027 investment plan; tender stays on hold
Baniyas Pilot Seawater Desalination Plant
Financial
16High
SYP 120M
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028·rami.youssef@psa.gov.sy
Escalate
Escalated
In 48 days2026-12-15
20 d
RSK-0022Material
Control-room fire systems not meeting civil-defence requirements
Aleppo 230 kV Substations Rehabilitation
Regulatory
15High
SYP 300M
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028·rami.youssef@psa.gov.sy
Mitigate
Open
In 79 days2027-01-15
9 d
RSK-0028Material
Possible termination of the MEP subcontractor
Hama National Hospital Upgrade & Extension
Contractual
15High
SYP 237.5M
Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014·fadi.aldroubi@psa.gov.sy
Mitigate
Open
In 28 days2026-11-25
10 d
RSK-0046Material
Bids 18% above the engineering estimate
Deir ez-Zor Suspension Bridge Reconstruction
Financial
15High
SYP 2.3B
Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036·wael.alkhawlani@psa.gov.sy
Mitigate
Open
In 33 days2026-11-30
5 d
RSK-0003
Late sign-off of service requirements by the owning ministries
Unified Government e-Services Platform
Stakeholder
12Medium
SYP 30M
Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004·lina.alattar@psa.gov.sy
Mitigate
Open
In 23 days2026-11-20
6 d
RSK-0006
Possible critical findings in the pre-launch penetration test
Citizen service centre staff resisting the new digital procedures
Unified Government e-Services Platform
Stakeholder
9Medium
SYP 7.5M
Ola Al-JandaliOla Al-JandaliChange Management SpecialistP-035·ola.aljandali@psa.gov.sy
Mitigate
In progress
In 110 days2027-02-15
13 d
RSK-0010
Mobile-app team competing with the platform for the same people
Unified Government e-Services Platform
Resource
9Medium
SYP 13M
Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004·lina.alattar@psa.gov.sy
Mitigate
Open
In 21 days2026-11-18
3 d
RSK-0048
Late signature of the government data centre hosting contract