Quality

Quality plans, inspections, non-conformance reports and corrective actions.

Working on:Planning and Statistics Authority
Open NCRs
12⁦6⁩ critical or high

Of ⁦16⁩ raised in 2026

First-time pass
⁦36%⁩

⁦64%⁩ with remarks · of ⁦22⁩ inspections

Corrective actions overdue
1

Of ⁦4⁩ open actions

Average time to close
30 days

From raising an NCR to closing it

Cost of poor quality
SYP 175.5M

Rework, retests and delay — 2026

NCR lifecycle

Drag a report to its next stage. It cannot go to verification without a corrective action, nor close before its actions are done and verified.

Open3 · ⁦3⁩ cards

Found, not yet investigated

Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.

Investigating4 · ⁦4⁩ cards

Root-cause analysis

⁦4⁩ of ⁦4⁩

Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.

Corrective action3 · ⁦3⁩ cards

Corrective action under way

Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.

Verifying2 · ⁦2⁩ cards

Checking the fix works

Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.

Closed4 · ⁦4⁩ cards

Closed after verification

Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.

Quality by project, and inspections

Acceptance criteria met in each project’s plan, inspection pass rate and open NCRs — and the inspection & review calendar.

Quality by project

Worst first · click the criteria to open the quality plan

ProjectCriteria metPass rateOpen NCRs

Inspections & reviews

Scheduled for the next two weeks, and the latest results

Upcoming
  • 302026-10

    Review of the handover file and documentation

    Document review · Ministry of Finance e-Archiving

  • 022026-11

    Design review of the redesigned foundation axes

    Design review · Douma Wastewater Treatment Plant

  • 042026-11

    Pre-launch penetration test

    Security test · Unified Government e-Services Platform

  • 082026-11

    Re-test of pit 2 tightness

    Site inspection · Aleppo 230 kV Substations Rehabilitation

  • 112026-11

    MEP first fix — level 3

    Site inspection · Hama National Hospital Upgrade & Extension

Latest results
  • 262026-10

    Basement retaining-wall inspection

    Site inspection · Sheikh Najjar Industrial City Rehabilitation

  • 242026-10

    Backfill compaction — zone 3

    Site inspection · Darayya Replacement Housing

  • 212026-10

    Waterproofing of the east roof

    Site inspection · Hama National Hospital Upgrade & Extension

  • 192026-10

    Flash test of panel batch 6

    Material test · 20 MW Qalamoun Solar Field

  • 192026-10

    Acceptance test of the wave-one services

    Acceptance test · Unified Government e-Services Platform

    Passed
  • 152026-10

    Acceptance of the control systems at the pumping station and main tank

    Site inspection · Madinat al-Salam Drinking-Water Network (Quneitra)

    Passed

Registers

Every NCR, inspection, plan, standard and corrective action — searchable, filterable, exportable.

Open
⁦12⁩ results
Export CSV
CriticalCorrective actionWorkmanshipEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy2026-09-18In 13 days2026-11-10SYP 45M
HighInvestigatingMaterialsEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy2026-10-06In 8 days2026-11-05SYP 16M
HighVerifyingWorkmanshipEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy2026-08-27In 2 days2026-10-30SYP 23M
HighInvestigatingDesignEng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy2026-09-12In 5 days2026-11-02SYP 19M
HighVerifyingDataNour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy2026-09-053 days overdue2026-10-25SYP 4.5M
HighOpenWorkmanshipEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy2026-10-27In 27 days2026-11-24SYP 10.8M
MediumOpenMaterialsEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy2026-10-22In 22 days2026-11-19SYP 5.3M
MediumOpenWorkmanshipEng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy2026-10-25In 18 days2026-11-15SYP 7M
MediumCorrective actionDocumentationEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy2026-09-242 days overdue2026-10-26—
MediumCorrective actionSoftwareEng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy2026-10-01In 6 days2026-11-03SYP 2.4M
Total · 12SYP 134.4M
⁦1⁩–⁦10⁩ of ⁦12⁩

Activity

What changed in the quality records in this session.

Latest quality changes

No changes on this screen yet.

Leak in oil pit 2 during the tightness test

NCR-2026-041

CriticalWorkmanshipOpen for ⁦40⁩ days
3

Step ⁦3⁩ of ⁦5⁩

Corrective action

What was found

The level dropped 0.6% in 24 h against a 0.1% limit; damp at two construction joints on the north wall.

Immediate containment

Test stopped, pit drained, the transformer kept off it until repaired.

Root cause

Water-stops were not fitted at two construction joints as per the approved drawings.

Corrective actions (⁦2⁩)

  • Inject the two joints with epoxy and fit external water-stops

    CA-2026-101 · Eng. Adnan Al-Mohammad

    60
    In 5 days2026-11-02
  • Add a water-stop hold point before every pour

    CA-2026-102 · Eng. Maher Al-Hamawi

    Done — awaiting verification
Owner
Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
Raised by
Eng. Adnan Al-MohammadEng. Adnan Al-MohammadSenior Site Engineer (Contractor)P-043adnan.almohammad@psa.gov.sy
Raised on
2026-09-18
Due
In 13 days2026-11-10
Vendor / contractor
Al-Shahbaa Construction & Rehabilitation Co.
From inspection
INS-2026-061
Cost of poor quality
SYP 45M
Esc