PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology

Digital Signature & e-Verification of Government Documents — Phase 1

Add to watchlist

Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.

Budget (BAC)

SYP 205M

Actual cost

SYP 199M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 199M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 205M split into spent, committed and left, with the estimate at completion

EAC SYP 199M
Revised request SYP 205M
  • Actual spendSYP 199M
  • Committed, not spentSYP 971K
  • Allotted, uncommittedSYP 0
  • Contingency availableSYP 6.2M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 192.5M
Original budgetwhen the first baseline was approved
SYP 205M
Approved budgetafter approved change requests
SYP 205M
Current budgetavailable to spend now
SYP 205M
Revised budgetif the pending changes are approved
SYP 205M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 200M
Contracts1 active contract
SYP 172.5M
Purchase orders⁦2⁩ orders
SYP 27.5M
Remaining budgetapproved less actual
SYP 6M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 199M
Accrualswork done, not yet invoiced
SYP 8M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 199M
ContingencySYP 4.1M drawn of SYP 10.3M
SYP 6.2M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 192.5M
ApprovedSYP 205M
Estimate at completionSYP 199M
Approved is SYP 12.5M (⁦6.5%⁩) above the estimate
The estimate at completion is SYP 6.5M (⁦3.4%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-01-23⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61031
  • WBS elements⁦5⁩ elements · P-2026-031.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦10⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 4.1M drawn of SYP 10.3M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 4.1M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance15.9116.1215.9215.31⁦+0.60⁩
2Analysis & design33.8034.0333.8333.22⁦+0.58⁩
3Build79.5479.8179.6179.00⁦+0.54⁩
4Testing & acceptance39.7740.0039.8139.19⁦+0.58⁩
5Launch & handover29.8330.0529.8529.24⁦+0.59⁩
Unallocated contingency6.150.000.003.08⁦+3.08⁩
Total205.00200.00199.03199.03⁦+5.97⁩

Budget split

WBS

SYP 205M

Budget

  • Management & governanceSYP 15.9M⁦8%⁩
  • Analysis & designSYP 33.8M⁦16%⁩
  • BuildSYP 79.5M⁦39%⁩
  • Testing & acceptanceSYP 39.8M⁦19%⁩
  • Launch & handoverSYP 29.8M⁦15%⁩
  • Unallocated contingencySYP 6.2M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2025-07-30⁩+30

SPI(t) ⁦0.94⁩ against the approved finish ⁦2025-06-30⁩

Planned valuePV
SYP 205M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 205M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 199M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 205M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+5.97⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.03
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 199M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+5.97⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 199M
  • If the rest goes to planSYP 199M
  • At cost and schedule performanceSYP 199M
  • The PM’s bottom-up estimateSYP 199M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 199M

Variance at completion: ⁦+5.97⁩ SYP M