PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology

Digital Signature & e-Verification of Government Documents — Phase 1

Add to watchlist

Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.

Budget (BAC)

SYP 205M

Actual cost

SYP 199M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 199M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project lifecycle and its gates

Current phase: Closure. Pick a gate on the track to review it.

  1. Gate into «Initiation»DecisionGoDate7 February 2024All criteria and required documents met.Pre-startComplete
  2. Gate into «Planning»DecisionGoDate7 April 2024All criteria and required documents met.InitiationComplete
  3. Gate into «Execution»DecisionGoDate18 June 2024All criteria and required documents met.PlanningComplete
  4. Gate into «Closure»DecisionGoDate25 May 2025All criteria and required documents met.ExecutionComplete
  5. ClosureCurrent stageCurrent stage

What each stage requires

The documents and approvals each gate asks for before the next stage.

G4PassedProject Management Office

Closure gate — deliverables accepted and handed over

4Execution5ClosureHeld ⁦2025-05-25⁩
84/100

Gate readiness

Meets the pass mark

Checklist

⁦7⁩ of ⁦7⁩ done

  • Deliverable completion certificates approved for every deliverableMandatory
  • Acceptance tests and handover to operations completeMandatory
  • Open commitments listed with a plan to close themMandatory
  • Deliverable-linked payments settledMandatory
  • Pilot run with no critical or high findingsMandatory
  • Users trained
  • Launch rollback plan

Required documents

⁦4⁩ of ⁦4⁩ approved

  • Deliverable completion certificatesApproved · V2
  • Project closure & handover formApproved · V3
  • Lessons-learned logApproved · V1
  • Benefits measurement planApproved · V2

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Deliverables acceptedweight ⁦35⁩%Met

    Evidence attached and accepted in the committee minutes.

    80
  • Quality & securityweight ⁦25⁩%Met

    Evidence attached and accepted in the committee minutes.

    83
  • Operations & handover readinessweight ⁦25⁩%Met

    Evidence attached and accepted in the committee minutes.

    86
  • User & training readinessweight ⁦15⁩%

    Evidence attached and accepted in the committee minutes.

    89

Approvers

Project Management Office

  • Dr. Reem Al-QabbaniPMO directorApproved
  • Ibrahim Al-SaeedProject ownerApproved
  • Eng. Khaled Al-KayyaliProject sponsorApproved