PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology

Digital Signature & e-Verification of Government Documents — Phase 1

Add to watchlist

Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.

Budget (BAC)

SYP 205M

Actual cost

SYP 199M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 199M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-05-02⁩
ApprovedPRJ-2026-031Digital Signature & e-Verification of Government Documents — Phase 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Digital Signature & e-Verification of Government Documents — Phase 1
Portfolio
Digital Government Services & Data Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Kinan Azzam

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-04-07⁩

Baseline finish

⁦2025-06-30⁩

Forecast finish

⁦2025-07-20⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2024-07-17⁩⁦2024-07-21⁩+4 days
Designs approved⁦2024-10-02⁩⁦2024-10-10⁩+8 days
Build complete⁦2025-01-26⁩⁦2025-02-08⁩+13 days
Testing & acceptance complete⁦2025-04-14⁩⁦2025-04-30⁩+16 days
Final handover⁦2025-06-30⁩⁦2025-07-20⁩+20 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2024-06-08⁩Kinan Azzam
Monitoring & reporting⁦4%⁩⁦2024-07-17⁩Ibrahim Al-Saeed
Business requirements⁦9%⁩⁦2024-08-24⁩Ibrahim Al-Saeed
Solution design⁦9%⁩⁦2024-10-02⁩Eng. Khaled Al-Kayyali
Release 1⁦13%⁩⁦2024-11-10⁩Eng. Khaled Al-Kayyali
Release 2⁦13%⁩⁦2024-12-18⁩Kinan Azzam
Integrations⁦13%⁩⁦2025-01-26⁩Ibrahim Al-Saeed
System testing⁦10%⁩⁦2025-03-06⁩Kinan Azzam
User acceptance testing⁦10%⁩⁦2025-04-14⁩Ibrahim Al-Saeed
Training & change⁦8%⁩⁦2025-05-22⁩Ibrahim Al-Saeed
Go-live & handover⁦7%⁩⁦2025-06-30⁩Eng. Khaled Al-Kayyali
Accepted with a certificate⁦100%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyKinan Azzam
Project ownerDeliverable status and acceptance datesFortnightlyKinan Azzam
PMOData and indicator updatesWeeklyKinan Azzam
BeneficiariesWhat changes and whenAt each milestoneKinan Azzam
Team memberRoleAllocation
Kinan AzzamProject manager⁦0%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Shorter government-document verification time42 minutes15 minutesEng. Lina Al-Attar
Higher citizen satisfaction with document e-verification64 %85 %Eng. Lina Al-Attar

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2024-05-02⁩ 14:47
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2024-05-06⁩ 10:49
3Technical acceptance — project ownerTechnical acceptanceIbrahim Al-SaeedProject ownerApproved—⁦2024-05-09⁩ 11:56
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-05-12⁩ 09:42
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2024-05-14⁩ 10:19
6Sponsor approvalTechnical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2024-05-19⁩ 14:17

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2024-05-06⁩

Technical acceptance — project owner

Ibrahim Al-Saeed

Approved⁦2024-05-09⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2024-05-12⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2024-05-14⁩

Sponsor approval

Eng. Khaled Al-Kayyali

Approved⁦2024-05-19⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Kinan Azzam on ⁦2024-05-02⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-05-06⁩ at ⁦10:49⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2024-05-09⁩ at ⁦11:56⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-05-12⁩ at ⁦09:42⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-05-14⁩ at ⁦10:19⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2024-05-19⁩ at ⁦14:17⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-05-02⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Kinan Azzam

  2. V1Returned for edit⁦2024-04-18⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Kinan Azzam