PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology
Digital Signature & e-Verification of Government Documents — Phase 1
Add to watchlist
Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.
1.00Schedule performance index · 1.001.03Cost performance index · 1.03
Forecast finish
2025-07-20
20 days behind baseline
Closure·Stage 5 of 5
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage