PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology

Digital Signature & e-Verification of Government Documents — Phase 1

Add to watchlist

Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.

Budget (BAC)

SYP 205M

Actual cost

SYP 199M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 199M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage
Fields required by the project’s stage (Closure): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Digital Signature & e-Verification of Government Documents — Phase 1

APPROVEDV2Approved ⁦2024-04-05⁩

1Project identity

Required at this stage
Project name
Digital Signature & e-Verification of Government Documents — Phase 1
Project code
PRJ-2026-031
Project sponsor
Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy
Project manager
Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy
Project owner
Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy
Portfolio & programme
Digital Government Services & Data PortfolioGovernment e-Services Programme
Type & methodology
Digital · Scrum
Current phase
5Closure

2Background & rationale

Required at this stage

⁦Phase 1 of digital signatures on government documents with a scannable verification code⁩, starting with civil-registry documents and school certificates.

3Objectives

Required at this stage
  1. 1Integrated digital government services for citizens

4Scope

Required at this stage

In scope

  • ⁦Phase 1 of digital signatures on government documents with a scannable verification code⁩, starting with civil-registry documents and school certificates.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Identity checks against the civil registry
  2. 2Integration with internal systems
  3. 3Accessibility and UX standards

6Deliverables

Required at this stage
1Project management plan⁦2024-04-25⁩
2Main deliverable — stage 1⁦2024-11-22⁩
3Main deliverable — final stage⁦2025-04-28⁩
4Final report⁦2025-06-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-04-05⁩
  2. Contract signed⁦2024-06-18⁩
  3. 50% of works complete⁦2024-11-22⁩
  4. Provisional acceptance⁦2025-05-25⁩
  5. Closure⁦2025-06-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP147.5M
  • Supervision & consulting⁦14.6%⁩SYP30M
  • Internal team⁦8.5%⁩SYP17.5M
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩SYP10M
The delivering body’s investment-plan allocationsTotalSYP205M

9Timeline

Required at this stage
Start
2024-04-077 April 2024
Baseline finish
2025-06-3030 June 2025
Duration
⁦15⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly