PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology

Digital Signature & e-Verification of Government Documents — Phase 1

Add to watchlist

Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.

Budget (BAC)

SYP 205M

Actual cost

SYP 199M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 199M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP198.9M⁦16⁩ elements
Unallocated contingencySYP6.2MSYP 10.3M
Budget at completionSYP205MPRJ-2026-031
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project469⁦2024-04-07⁩⁦2025-07-20⁩⁦100%⁩198.85199.03—
1
Phase105⁦2024-04-07⁩⁦2024-07-21⁩⁦100%⁩15.9115.92—
1.1
WBS element65⁦2024-04-07⁩⁦2024-06-11⁩⁦100%⁩7.957.960 / 1
1.2
WBS element65⁦2024-05-17⁩⁦2024-07-21⁩⁦100%⁩7.957.961 / 2
2
Phase105⁦2024-06-27⁩⁦2024-10-10⁩⁦100%⁩33.8033.83—
2.1
WBS element65⁦2024-06-27⁩⁦2024-08-31⁩⁦100%⁩16.9016.921 / 1
2.2
WBS element65⁦2024-08-06⁩⁦2024-10-10⁩⁦100%⁩16.9016.921 / 2
3
Phase145⁦2024-09-16⁩⁦2025-02-08⁩⁦100%⁩79.5479.61—
3.1
WBS element64⁦2024-09-16⁩⁦2024-11-19⁩⁦100%⁩26.5126.541 / 1
3.2
WBS element65⁦2024-10-26⁩⁦2024-12-30⁩⁦100%⁩26.5126.541 / 1
3.3
WBS element64⁦2024-12-06⁩⁦2025-02-08⁩⁦100%⁩26.5126.541 / 2
4
Phase105⁦2025-01-15⁩⁦2025-04-30⁩⁦100%⁩39.7739.81—
4.1
WBS element65⁦2025-01-15⁩⁦2025-03-21⁩⁦100%⁩19.8919.901 / 1
4.2
WBS element65⁦2025-02-24⁩⁦2025-04-30⁩⁦100%⁩19.8919.901 / 2
5
Phase105⁦2025-04-06⁩⁦2025-07-20⁩⁦100%⁩29.8329.85—
5.1
WBS element65⁦2025-04-06⁩⁦2025-06-10⁩⁦100%⁩14.9114.931 / 1
5.2
WBS element65⁦2025-05-16⁩⁦2025-07-20⁩⁦100%⁩14.9114.931 / 1
Total⁦100%⁩198.85199.03