PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology
Digital Signature & e-Verification of Government Documents — Phase 1
Add to watchlistPhase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.
Project managerKinan AzzamProject sponsorEng. Khaled Al-KayyaliProgrammeGovernment e-Services Programme
Budget (BAC)
SYP 205M
Actual cost
SYP 199M
97% of budget
Progress
100%Awaiting acceptance 0%
Estimate at completion
SYP 199M
SPI · CPI
1.00Schedule performance index · 1.001.03Cost performance index · 1.03
Forecast finish
2025-07-20
20 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to workSYP198.9M16 elements
Unallocated contingencySYP6.2MSYP 10.3M
Budget at completionSYP205MPRJ-2026-031
Weighted progress100%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Total100%198.85199.03