Digital Signature & e-Verification of Government Documents — Phase 1
Add to watchlistPhase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.
Budget (BAC)
Actual cost
97% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-07-17 | 2024-07-21 | +4 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2024-10-02 | 2024-10-10 | +8 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-01-26 | 2025-02-08 | +13 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2025-04-14 | 2025-04-30 | +16 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2025-06-30 | 2025-07-20 | +20 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline031-D1 | 4% | CRT-031-01 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Ibrahim Al-Saeed | 2024-06-08 | V1 | 3 of 3 |
| Monitoring & reporting031-D2 | 4% | CRT-031-02 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2024-07-17 | V1 | 3 of 3 |
| Business requirements031-D3 | 9% | CRT-031-03 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2024-08-24 | V1 | 3 of 3 |
| Solution design031-D4 | 9% | CRT-031-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Ibrahim Al-Saeed | 2024-10-02 | V1 | 3 of 3 |
| Release 1031-D5 | 13% | CRT-031-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Ibrahim Al-Saeed | 2024-11-10 | V1 | 3 of 3 |
| Release 2031-D6 | 13% | CRT-031-06 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Ibrahim Al-Saeed | 2024-12-18 | V1 | 3 of 3 |
| Integrations031-D7 | 13% | CRT-031-07 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2025-01-26 | V1 | 3 of 3 |
| System testing031-D8 | 10% | CRT-031-08 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Ibrahim Al-Saeed | 2025-03-06 | V1 | 3 of 3 |
| User acceptance testing031-D9 | 10% | CRT-031-09 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2025-04-14 | V1 | 3 of 3 |
| Training & change031-D10 | 8% | CRT-031-10 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2025-05-22 | V1 | 3 of 3 |
| Go-live & handover031-D11 | 7% | CRT-031-11 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Ibrahim Al-Saeed | 2025-06-30 | V1 | 3 of 3 |
| Total · 11 | 100% |