PRJ-2026-009At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Government Cloud & Ministry Systems Migration

Add to watchlist

Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.

Budget (BAC)

SYP 1.3B

Actual cost

SYP 629.9M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1.3B

+SYP 40.2M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Government Cloud & Ministry Systems Migration

PRJ-2026-009 · Digital Transformation Sector · Operational · WP-2025-009

In progressAt risk4ExecutionProject manager: Eng. George Haddad · Sponsor: Eng. Khaled Al-Kayyali
Progress
⁦47%⁩ / ⁦53%⁩
SPI · CPI
0.89 · 0.97
Spend
SYP 629.9M / SYP 1.3B
Estimate at completion
SYP 1.3B

Schedule

⁦6%⁩ behind⁦47%⁩

Planned to date ⁦53%⁩

Forecast finish: 2027-03-21 · 21 days late

SPI0.89Schedule performance index · 0.89CPI0.97Cost performance index · 0.97

Health dimensions

At risk

Last update: 2026-10-24 · Up to date

Deliverables

⁦5⁩ of ⁦8⁩ due deliverables accepted on time (⁦63%⁩)

Next milestones

  • Build complete2026-12-20
  • Testing & acceptance complete2027-02-02
  • Final handover2027-03-18

Top risks

  • Government cloud resource cost above estimate9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 1.3bn: 0 on track and 0 red or critical. Weighted progress is 47% against 53% planned, spend SYP 629.9M, and EAC SYP 1.34bn (SYP 40.2M over).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Eng. George Haddad in MunjazInternal

Status: At risk ·Project page