Project status card
28 October 2026
Government Cloud & Ministry Systems Migration
PRJ-2026-009 · Digital Transformation Sector · Operational · WP-2025-009
- Progress
- 47% / 53%
- SPI · CPI
- 0.89 · 0.97
- Spend
- SYP 629.9M / SYP 1.3B
- Estimate at completion
- SYP 1.3B
Schedule
Planned to date 53%
Forecast finish: 2027-03-21 · 21 days late
SPI0.89Schedule performance index · 0.89CPI0.97Cost performance index · 0.97Health dimensions
Last update: 2026-10-24 · Up to date
Deliverables
5 of 8 due deliverables accepted on time (63%)
Next milestones
- Build complete2026-12-20
- Testing & acceptance complete2027-02-02
- Final handover2027-03-18
Top risks
- Government cloud resource cost above estimate9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 1.3bn: 0 on track and 0 red or critical. Weighted progress is 47% against 53% planned, spend SYP 629.9M, and EAC SYP 1.34bn (SYP 40.2M over).
No project is more than a month behind baseline.