PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-01-18⁩
ApprovedCR-2026-003Add two spare bays at substation 4

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Aleppo 230 kV Substations Rehabilitation
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The change

TitleAuto-filled
Add two spare bays at substation 4
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Maher Al-Hamawi
Raised onAuto-filled
⁦2026-01-18⁩

Reason

A directive to add two standby bays at substation 4 as loads grow in the Aleppo industrial area

Justification

The existing bays cannot carry the expected load; without the two bays rationing recurs in about a third of the neighbourhoods served

2Impact analysis

Cost

+SYP 535M

Schedule

+45 days

Risk

20 → 15

Benefits

+22%

Risk impact

The two bays are designed to Civil Defence rules from the start

Benefits impact

Two standby bays that lift supply reliability in 28 neighbourhoods

3The approval decision

The PMO’s recommendation

The national PMO recommends approval: the change serves the core-infrastructure objective directly

Change Committee decision
Approve
Decided on
⁦2026-02-05⁩
Decision number
DEC-2026-005

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2026-01-18⁩ 12:33
2Project managerTechnical acceptanceEng. Maher Al-HamawiProject managerApproved—⁦2026-01-19⁩ 14:47
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-01-20⁩ 09:54
4Financial impactFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-01-21⁩ 13:52
5Contractual impactFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-01-25⁩ 14:29
6Change CommitteeTechnical acceptanceDr. Ziad Al-AtassiChange CommitteeApproved—⁦2026-01-26⁩ 12:15
7National Projects Steering CommitteeTechnical acceptanceDr. Samer Al-DaqqarNational Projects Steering CommitteeApproved—⁦2026-01-27⁩ 09:30

Signatures

Project manager

Eng. Maher Al-Hamawi

Approved⁦2026-01-19⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-01-20⁩

Financial impact

Rasha Al-Mudarres

Approved⁦2026-01-21⁩

Contractual impact

Abdullah Al-Ujaili

Approved⁦2026-01-25⁩

Change Committee

Dr. Ziad Al-Atassi

Approved⁦2026-01-26⁩

National Projects Steering Committee

Dr. Samer Al-Daqqar

Approved⁦2026-01-27⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2026-01-18⁩

  1. Technical acceptance

    Project manager

    Eng. Maher Al-Hamawi · Project manager

    Approved · ⁦2026-01-19⁩ at ⁦14:47⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-01-20⁩ at ⁦09:54⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-01-21⁩ at ⁦13:52⁩

  4. Financial approval

    Contractual impact

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-01-25⁩ at ⁦14:29⁩

  5. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Approved · ⁦2026-01-26⁩ at ⁦12:15⁩

  6. Technical acceptance

    National Projects Steering Committee

    Dr. Samer Al-Daqqar · National Projects Steering Committee

    On the path because: Cost impact above the Change Committee’s authority?From the authority matrix

    Approved · ⁦2026-01-27⁩ at ⁦09:30⁩

Steps that do not apply to this record

  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-02-05⁩

    Approved by the committee

    Eng. Maher Al-Hamawi

  2. V1Returned for edit⁦2026-01-18⁩

    The request as raised

    Eng. Maher Al-Hamawi