PRJ-2026-002Off track4ExecutionConstructionStalledDelivered by:Ministry of Public Works and Housing

Darayya Replacement Housing

Remove from watchlist

Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 29.5B

Actual cost

SYP 13.3B

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 31.7B

+SYP 2.2B

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Periodic update — September 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
PSA-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-10-02⁩
ApprovedUPD-002-2026-09Periodic update — September 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
Darayya Replacement Housing
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦40%⁩

+3 pts on the last period

Planned to date

⁦48%⁩

SPI

0.83

Actual cost

SYP 12.5B

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

Prefilled from the August 2026 card — edit it if it changed

2Status

Overall healthAuto-filled
Off track
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2027-09-12⁩

The PM’s comment on the statusFilled by the project manager

The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.

Prefilled from the August 2026 card — edit it if it changed

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
RSK-0015Steel and concrete price rises driving price-adjustment claims20Eng. Qasem Al-Hariri
RSK-0016Late hand-over of the northern plot and utility diversions in blocks 3 and 420Eng. Wassim Al-Azm
RSK-0017Contractor claim for a 120-day extension with compensation16Omar Al-Nahhas
RSK-0018Safety incidents around cranes and deep excavations10Eng. Qasem Al-Hariri
CodeImpedimentSeverity
ISS-0116Excavation clashes with the high-voltage line in block 4High
ISS-0117Residents complaining about traffic diversions around the siteMedium
ISS-0118Late approval of the school and health-centre designsMedium

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

Approve change request CR-2026-012 for three integration engineers (SYP 24.5M), and the President of the Authority to press the Ministry of Interior on the civil-registry test environment.

Prefilled from the August 2026 card — edit it if it changed

Includes financial supportAuto-filled
Yes

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsSubmitted—⁦2026-10-02⁩ 11:38
2PMO checkMethodology reviewMariam Al-ZoubiPMO — analystApprovedThe reading agrees with the schedule and finance.⁦2026-10-04⁩ 13:58
3Sponsor review & approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2026-10-06⁩ 14:05

Signatures

PMO check

Mariam Al-Zoubi

Approved⁦2026-10-04⁩

Sponsor review & approval

Salma Al-Zaim

Approved⁦2026-10-06⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Eng. Qasem Al-Hariri on ⁦2026-10-02⁩

  1. Methodology review

    PMO check

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-10-04⁩ at ⁦13:58⁩

    The reading agrees with the schedule and finance.

  2. Technical acceptance

    Sponsor review & approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2026-10-06⁩ at ⁦14:05⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-10-02⁩

    The card as the PM filled it

    • Prefilled from the previous period’s card and the live data

    Eng. Qasem Al-Hariri

Only one version so far.