Project status card
28 October 2026
Darayya Replacement Housing
PRJ-2026-002 · Development Projects Follow-up Sector · Strategic · WP-2024-002
- Progress
- 42% / 51%
- SPI · CPI
- 0.82 · 0.93
- Spend
- SYP 13.3B / SYP 29.5B
- Estimate at completion
- SYP 31.7B
Schedule
Planned to date 51%
Forecast finish: 2027-09-12 · 74 days late
SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93Health dimensions
Last update: 2026-10-26 · Up to date
Deliverables
5 of 9 due deliverables accepted on time (56%)
Next milestones
- Build complete2027-01-17
- Testing & acceptance complete2027-06-19
- Final handover2027-09-29
Top risks
- Steel and concrete price rises driving price-adjustment claims20
- Late hand-over of the northern plot and utility diversions in blocks 3 and 420
- Contractor claim for a 120-day extension with compensation16
- Safety incidents around cranes and deep excavations10
Open impediments
- Excavation clashes with the high-voltage line in block 4 · Escalated
- Residents complaining about traffic diversions around the site · In progress
- Late approval of the school and health-centre designs · Open
Decisions and changes waiting
- Review certificate 28 — Darayya replacement housing
Copilot summary
The scope holds 1 project with a budget of SYP 29.5bn: 0 on track and 1 red or critical. Weighted progress is 42% against 51% planned, spend SYP 13.32bn, and EAC SYP 31.72bn (SYP 2.22bn over).
1 project is more than a month behind baseline; the worst: Darayya Replacement Housing (74 days).