PRJ-2026-031On track5ClosureScrumCompletedDelivered by:Ministry of Communications and Information Technology

Digital Signature & e-Verification of Government Documents — Phase 1

Add to watchlist

Phase 1 of digital signatures on government documents with a scannable verification code, starting with civil-registry documents and school certificates.

Budget (BAC)

SYP 205M

Actual cost

SYP 199M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 199M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
PSA-PMO-F12
Template edition
2.0
Version
V2
Form date
⁦2025-09-28⁩
ApprovedPRJ-2026-031Digital Signature & e-Verification of Government Documents — Phase 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Digital Signature & e-Verification of Government Documents — Phase 1
Portfolio
Digital Government Services & Data Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Kinan Azzam

1PerformanceAuto-filled

Approved budget

SYP 205M

Actual cost

SYP 199M

Cost variance

+SYP 6M

Schedule variance

+20 days

Post-implementation questionVerdictAnswer
Did the project meet its goal?YesYes. Digital signature and e-verification went live with nine services; over 41K government documents verified through them in year one.
Was it delivered within budget?YesDelivered for SYP 199M against 205M, 20 days after baseline.
Are the benefits showing?Partly82% realised: satisfaction 82% vs 85% target, 18 minutes to verify a document vs 15.
Were the lessons captured?YesThree lessons: civil-registry test environments, payments tied to acceptance, the vendor team.
What to improve next time?PartlyAn SMS alert before a document expires, and linking each signed document to the citizen’s account on the unified platform.

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesDoneBasel Al-MahayniFinal acceptance of 9 deliverables, no open findings
Financial settlementDoneOmar Al-NahhasActual SYP 199M of 205M — SYP 6M returned to the investment plan
Contracts closedDoneOmar Al-NahhasContract PSA/2024/009 closed, performance bond released
Documents archivedDoneKinan Azzam64 documents archived with their classification
Lessons learnedDoneKinan Azzam3 lessons published, cited 13 times since
Benefits handed to their ownerDoneEng. Lina Al-AttarEng. Lina Al-Attar owns two benefits with a 24-month plan
Final reportDoneKinan AzzamFinal report approved by the sponsor and the PMO
BenefitNew ownerHandover
Shorter government-document verification timeEng. Lina Al-AttarAccepted
Higher citizen satisfaction with document e-verificationEng. Lina Al-AttarAccepted

3Open commitments

CommitmentOwnerDue
No open commitments — the file is complete

4Lessons learnedAuto-filled

  1. Book civil-registry test environments three months before build
  2. Tie payments to accepted deliverables, not elapsed time

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2025-09-16⁩ 12:03
2Closure file completenessMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-09-21⁩ 14:53
3Handover accepted — project ownerTechnical acceptanceIbrahim Al-SaeedProject ownerApproved—⁦2025-09-22⁩ 09:00
4Final financial settlementFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-09-23⁩ 09:06
5Contracts closed, guarantees releasedFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-09-25⁩ 10:43
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-10-01⁩ 12:21

Signatures

Closure file completeness

Mariam Al-Zoubi

Approved⁦2025-09-21⁩

Handover accepted — project owner

Ibrahim Al-Saeed

Approved⁦2025-09-22⁩

Final financial settlement

Rasha Al-Mudarres

Approved⁦2025-09-23⁩

Contracts closed, guarantees released

Abdullah Al-Ujaili

Approved⁦2025-09-25⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-10-01⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F12 · version V2

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Submitted by Kinan Azzam on ⁦2025-09-16⁩

  1. Methodology review

    Closure file completeness

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-09-21⁩ at ⁦14:53⁩

  2. Technical acceptance

    Handover accepted — project owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2025-09-22⁩ at ⁦09:00⁩

  3. Financial approval

    Final financial settlement

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-23⁩ at ⁦09:06⁩

  4. Financial approval

    Contracts closed, guarantees released

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-09-25⁩ at ⁦10:43⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-10-01⁩ at ⁦12:21⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-09-28⁩

    The approved closure file

    Kinan Azzam

Only one version so far.