PRJ-2026-009At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Government Cloud & Ministry Systems Migration

Add to watchlist

Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.

Budget (BAC)

SYP 1.3B

Actual cost

SYP 629.9M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1.3B

+SYP 40.2M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-05-30⁩
ApprovedPRJ-2026-009Government Cloud & Ministry Systems Migration

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-009
Project
Government Cloud & Ministry Systems Migration
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. George Haddad

1Objective

Background

Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.

Project objectives

  1. Sound governance and effective follow-up of projects and data

2Scope

In scope

  • Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-06-27⁩
Main deliverable — stage 1⁦2026-04-22⁩
Main deliverable — final stage⁦2026-12-01⁩
Final report⁦2027-02-28⁩
MilestoneDate
Charter approved⁦2025-05-30⁩
Contract signed⁦2025-09-11⁩
50% of works complete⁦2026-04-22⁩
Provisional acceptance⁦2027-01-08⁩
Closure⁦2027-02-28⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Khaled Al-Kayyali
Project ownerAuto-filled
Eng. Mazen Kassab
Project managerAuto-filled
Eng. George Haddad
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 935M
Supervision & consultingSYP 182.5M
Internal teamSYP 117.5M
Contingency reserve (5%)SYP 65M
Approved budgetSYP 1.3B

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. George HaddadDirector, Data Centres & Government NetworkSubmitted—⁦2025-05-21⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2025-05-24⁩ 12:30
3Project ownerTechnical acceptanceEng. Mazen KassabProject ownerApproved—⁦2025-05-27⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-05-28⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2025-05-30⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2025-05-24⁩

Project owner

Eng. Mazen Kassab

Approved⁦2025-05-27⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2025-05-28⁩

Sponsor approval

Eng. Khaled Al-Kayyali

Approved⁦2025-05-30⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. George Haddad on ⁦2025-05-21⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2025-05-24⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Mazen Kassab · Project owner

    Approved · ⁦2025-05-27⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-05-28⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2025-05-30⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-05-30⁩

    Approved version

    • PMO comments addressed

    Eng. George Haddad

  2. V1Returned for edit⁦2025-05-11⁩

    First draft

    • Returned to detail the budget

    Eng. George Haddad