PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-02-04⁩
ApprovedDMD-2026-006Sheikh Najjar Industrial City Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Sheikh Najjar Industrial City Rehabilitation
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Youssef Shehabi

1The proposalAuto-filled

TitleAuto-filled
Sheikh Najjar Industrial City Rehabilitation
Proposed byAuto-filled
Eng. Youssef Shehabi
DepartmentAuto-filled
Governorate Projects Directorate
Submitted onAuto-filled
⁦2024-02-04⁩
Proposal numberAuto-filled
DMD-2026-006

2Justification

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

3Objectives

  1. Stimulate growth, restore production and attract investment
  2. Rehabilitate core energy, water and transport infrastructure

Strategic objectives served

  • SO-1.1 — Stimulate growth, restore production and attract investment
  • SO-2.1 — Rehabilitate core energy, water and transport infrastructure

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 7.2B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 5.1B
Supervision & consultingSYP 1B
Internal teamSYP 642.5M
Contingency reserve (5%)SYP 357.5M
TotalSYP 7.2B

6Initial risks

RiskLevelProposed response
Ground-improvement costs up after the geotechnical surveyHighTreated in the risk management plan
Late works approvals from Aleppo GovernorateMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Youssef ShehabiSenior Project Manager — Governorate ProjectsSubmitted—⁦2024-02-04⁩ 14:59
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2024-02-06⁩ 12:09
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-02-08⁩ 13:16
4Portfolio manager reviewTechnical acceptanceEng. Fadi Al-DroubiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-02-13⁩ 14:23
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-02-15⁩ 14:35
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-02-19⁩ 10:37

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2024-02-06⁩

PMO review

Mariam Al-Zoubi

Approved⁦2024-02-08⁩

Portfolio manager review

Eng. Fadi Al-Droubi

Approved⁦2024-02-13⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2024-02-15⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-02-19⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Youssef Shehabi on ⁦2024-02-04⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2024-02-06⁩ at ⁦12:09⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-02-08⁩ at ⁦13:16⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Fadi Al-Droubi · Portfolio manager

    Approved · ⁦2024-02-13⁩ at ⁦14:23⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-02-15⁩ at ⁦14:35⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-02-19⁩ at ⁦10:37⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-02-25⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Youssef Shehabi

  2. V1Returned for edit⁦2024-02-04⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Youssef Shehabi