Project status card
28 October 2026
Sheikh Najjar Industrial City Rehabilitation
PRJ-2026-006 · Local Development & Governorates Sector · Strategic · WP-2024-006
- Progress
- 39% / 50%
- SPI · CPI
- 0.78 · 0.89
- Spend
- SYP 3.1B / SYP 7.2B
- Estimate at completion
- SYP 8B
Schedule
Planned to date 50%
Forecast finish: 2027-07-04 · 95 days late
SPI0.78Schedule performance index · 0.78CPI0.89Cost performance index · 0.89Health dimensions
Last update: 2026-10-23 · Up to date
Deliverables
4 of 9 due deliverables accepted on time (44%)
Next milestones
- Build complete2027-01-11
- Testing & acceptance complete2027-04-23
- Final handover2027-06-30
Top risks
- Ground-improvement costs up after the geotechnical survey16
- Late works approvals from Aleppo Governorate12
Open impediments
- Foundation works stopped awaiting works approvals · Escalated
- Neighbouring factories objecting to the service-road route · Open
Decisions and changes waiting
- CR-2026-007 · Additional ground improvement after the geotechnical survey
Copilot summary
The scope holds 1 project with a budget of SYP 7.15bn: 0 on track and 1 red or critical. Weighted progress is 39% against 50% planned, spend SYP 3.13bn, and EAC SYP 8.03bn (SYP 883.7M over).
1 project is more than a month behind baseline; the worst: Sheikh Najjar Industrial City Rehabilitation (95 days).