PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Sheikh Najjar Industrial City Rehabilitation

PRJ-2026-006 · Local Development & Governorates Sector · Strategic · WP-2024-006

StalledOff track4ExecutionProject manager: Eng. Youssef Shehabi · Sponsor: Eng. Bashir Al-Tai
Progress
⁦39%⁩ / ⁦50%⁩
SPI · CPI
0.78 · 0.89
Spend
SYP 3.1B / SYP 7.2B
Estimate at completion
SYP 8B

Schedule

⁦11%⁩ behind⁦39%⁩

Planned to date ⁦50%⁩

Forecast finish: 2027-07-04 · 95 days late

SPI0.78Schedule performance index · 0.78CPI0.89Cost performance index · 0.89

Health dimensions

Off track

Last update: 2026-10-23 · Up to date

Deliverables

⁦4⁩ of ⁦9⁩ due deliverables accepted on time (⁦44%⁩)

Next milestones

  • Build complete2027-01-11
  • Testing & acceptance complete2027-04-23
  • Final handover2027-06-30

Top risks

  • Ground-improvement costs up after the geotechnical survey16
  • Late works approvals from Aleppo Governorate12

Open impediments

  • Foundation works stopped awaiting works approvals · Escalated
  • Neighbouring factories objecting to the service-road route · Open

Decisions and changes waiting

  • CR-2026-007 · Additional ground improvement after the geotechnical survey

Copilot summary

The scope holds 1 project with a budget of SYP 7.15bn: 0 on track and 1 red or critical. Weighted progress is 39% against 50% planned, spend SYP 3.13bn, and EAC SYP 8.03bn (SYP 883.7M over).

1 project is more than a month behind baseline; the worst: Sheikh Najjar Industrial City Rehabilitation (95 days).

Planning and Statistics Authority · prepared by Eng. Youssef Shehabi in MunjazInternal

Status: Off track ·Project page